CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

July 15, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

 

    • Section 3 is 95% completed.
    • Tentatively set for Tuesday, July 20th construction will switch into Section 4, (Section 4 is the southeast corner of the intersection). Construction work in Section 4 will take 2-3 weeks.
    • Once work is completed in Section 4 Karvo Paving Company will complete asphalt paving and landscaping.
    • Traffic will be maintained.
    • Project completion date is scheduled for September 2010.

 

Contact Information:

Field Office 440- 230-9520

 

 

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

July 1, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

 

    • Construction is now in Phase 4 at the northwest quadrant of the intersection.
    • Two-way traffic is being maintained on Royalton Road and on W. 130th Street.
    • New curb will be installed tomorrow, July 2nd followed by under-drain and base

course asphalt.

    • New sidewalk, curb ramps and driveway aprons will then be placed.
    • Construction will then move to the final phase at the southwest quadrant.

 

Contact Information:

Field Office 440- 230-9520

 

 

 

CONSTRUCTION PROJECT UPDATE


ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT NORTH ROYALTON & STRONGSVILLE


DATE

June 1, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS


 Construction is continuing at the northeast quadrant of the intersection.
 Two-way traffic will be maintained.
 During Phase 2 westbound Royalton Road traffic will not be permitted to turn right onto northbound W. 130th Street and southbound W. 130th
Street traffic will not be permitted to turn left onto eastbound Royalton Road.
 Message boards and alternate route signs have been placed.


Contact Information:
Field Office 440- 230-9520




 

 

 

CONSTRUCTION PROJECT UPDATE
ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT
NORTH ROYALTON & STRONGSVILLE
DATE

May 24, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

 Karvo Construction Company has completed Phase I construction
at the southeast quadrant of the intersection.
 Traffic was switched to the Phase 2 plan on Friday, May 21st.
 Construction will be commencing at the northeast quadrant Monday, May 24th
two-way traffic will again be maintained.
 During Phase 2, westbound Royalton Road traffic will not be permitted to turn
right onto northbound W. 130th Street.
 Southbound W. 130th Street traffic will not be permitted to turn left onto eastbound
 Royalton Road.
 Alternate route signs have been placed.

Contact Information:
Field Office 440- 230-9520




 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

May 21, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

    • Karvo Construction Company will be working on the north east quadrant.
    • No westbound right turns from State Route 82 to West 130th Street.
    • No southbound left turns from West 130th Street to State Rout 82.
    • Alternate route signing will be posted.

 

Contact Information:

Field Office 440- 230-9520

 

 

 

 

                    CONSTRUCTION PROJECT UPDATE
ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT NORTH ROYALTON & STRONGSVILLE


DATE

May 3, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

 Karvo Construction Company continues construction work at the south east
quadrant of the intersection.
 Two-way traffic is being maintained through out the course of construction.
 Placement of concrete curb and asphalt pavement is scheduled for the first week
in May followed by placement of under drain.
 When Phase I of construction is completed, Karvo Construction Co. will begin
Phase 2 at the north east quadrant of the intersection.



Contact Information:
Field Office 440- 230-9520

 

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

April 1, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

  • Work has commenced by Karvo Construction Company at the south east quadrant of
  • The intersection.

  • Phase 1 detour was put into effect on March 31, 2010.
  • Two way traffic will be maintained at all times throughout the course construction.

Contact Information:

Field Office 440- 230-9520

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

March 29, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

  • Implementation of the scheduled work zone for March 25, 2010 has been delayed due to weather.
  • On March 30, 2010 the layout work for the temporary traffic zone will resume if weather conditions permit.

Contact Information:

Field Office 440- 230-9520

 

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

March 19, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

  • Work by Karvo Construction Company
  • Layout work for the temporary traffic zone will occur on March 25, 2010 along with message boards.
  • Temporary traffic zone for Phase 1 along with construction work will occur in the south east quadrant of the intersection on March 26, 2010.
  • Two way traffic will be maintained at all times throughout the course of construction with some adjustment to the number of lanes.

Contact Information:

Field Office 440- 230-9520

.

 

 

 

                  CONSTRUCTION PROJECT UPDATE
       ROYALTON ROAD/W. 130TH STREET INTERSECTION                IMPROVEMENT NORTH ROYALTON & STRONGSVILLE
 

DATE

March 9, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS


 Work by Karvo Construction and sub-contractor Martin Enterprises has been suspended until April 6, 2010.
 Work by Miller Cable on the installation of temporary signalization is possible throughout the remainder of March.
 

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

March 2, 2010

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

 

  • Sub-contractor Martin Enterprises placed 12", 18"and 21" storm sewer, catch basins and manholes.
  • Installation of sanitary sewer lateral connections.
  • Sub-contractor Miller Cable will continue with placement of temporary work zone traffic signalization.
  • Work to take place in March:
    • Martin Enterprises will continue with placement of storm sewer.
    • Miller Cable will continue with the installation of temporary work zone traffic signalization.

 

 

CONSTRUCTION PROJECT UPDATE

ROYALTON ROAD/W. 130TH STREET INTERSECTION IMPROVEMENT

NORTH ROYALTON & STRONGSVILLE

DATE

November 2, 2009

NOTICE TO PROCEED

October 5, 2009

START DATE

October 5, 2009

COMPLETION DATE

September 10, 2010

PROJECT AMOUNT

$2,213,351.74

PROGRESS

  • Message boards have been erected on Royalton Road informing eastbound and westbound motorist that the construction project will begin October 12, 2009, and to expect delays.
  • Pre-construction video has been made.
  • Construction right-of-way limits and proposed sanitary sewer staked.
  • Construction zone set for October 26, 2009, closing of the curb lane to westbound Royalton Road traffic west of the intersection.
  • On October 28, 2009 Sub-Contractor Martin Enterprises will begin installation of the sanitary sewer.
  • Work to take place in November:
  • The continuation of the installation of the sanitary sewer.

 

 