CROCKER ROAD-STEARNS ROAD EXTENSION

PRE-CON

Description: Creating an extension of Crocker Road-Stearns Road from Center Ridge Road to Lorain, and the widening of Stearns Road from Lorain to I-480 in the Cities of North Olmsted and Westlake.

 

Contractor: Fabrizi Trucking & Paving Co.

Area Engineer: Mike Tworzydlo

Project Engineer: Mark Rinderman

Project Cost: $13,299,797.20

Notice to Proceed: March 1, 2007

Start Date: March 1, 2007

Completion Date: September 1, 2009

Funding: Federal Highway Administration through NOACA & Cuyahoga County

 

Notes: Field Office is at the Kacirek Funeral Home

1. Start clearing from Lorain Road north

2. Then begin placing the storm sewers

3. Then begin working south from Center Ridge Road

4. Finally, work on section between I-480 and Lorain

Signs will be placed by I-480 and on the NW corner of Crocker/Center Ridge

 

Traffic will be maintained with one lane for both directions.

 

 

 

 

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • April 23, 2007

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299.797.20

PROGRESS

  • Fabrizi is currently placing a new storm sewer on the east side of Stearns Road from I-480 to Lorain Road, per Pre-Phase.
  • Water services and hydrants on the east side have yet to be relocated per Pre-Phase.
  • Temporary walk is being installed on left side per Phase I work.
  • Two-way traffic is being maintained during work hours using temporary signals, expect minor delays.
  • Power lines are being relocated at the area of Lorain/Stearns.
  • Dominion East Ohio Gas is on the project to relocate portions of main on Stearns, south of Lorain.
  • Crocker Road Extension has been cleared of trees from Lorain Road to Center Ridge Road and the area is currently being drained.
  • Progress schedule indicates temporary pavement construction starting early May on Stearns from I-480 to Lorain Road per Phase I.
  • After the installation of the temporary pavement, two-way traffic will be diverted to west side of roadway per Phase 2, and will be maintained.
  • Drainage work is to start at the north end of Crocker Road Extension in May.

 

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • May 24, 2007

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • Fabrizi is currently placing a new storm sewer on the east side of Stearns Road from I-480 to Lorain Road, per Pre-Phase.
  • Catch Basins and storm sewer crossovers are being placed in same area.
  • Cleanouts for storm and sanitary laterals are being relocated. However, water services and hydrants on east side have yet to be relocated per Pre-Phase.
  • Two-way traffic is being maintained during work hours using temporary signals. Expect minor delays.
  • Placement of new storm sewer in progress on Lorain Road.
  • Various lanes on Lorain will be closed during sewer work with two-way traffic being maintained at all times.
  • Dominion East Ohio Gas is relocating portion of main on Stearns, south of Lorain.
  • WOW and Time Warner are working on Stearns to relocate utility lines.
  • New storm sewers, culverts and earth embankment for the Proposed Crocker-Stearns Extension from Lorain to Center Ridge are being reconstructed
  • No traffic restrictions on Center Ridge Road.

NOTES

 

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

CONTINUED

  • The temporary pavement construction on Stearns from I-480 to Lorain has been pushed back to the second week in June due to utility relocation.
  • After temporary pavement is installed, two-way traffic will be diverted to the west side of the roadway.
  • Traffic will be shifter onto temporary pavement along the north side of Lorain Road in July for construction of new pavement on south side.

Progress schedule indicates that the new pavement construction will begin on Stearns in July and on the south side of Lorain in August

 

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Monday, June 25, 2007

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • The trunk sewer install is nearly complete on the east side of Stearns Road from I-480 to Lorain Road.
  • Catch basins, storm sewer crossovers and residential laterals are placed in same area, with cleanout relocation if necessary.
  • Box culver installation south of Lorain to begin within 2 weeks.
  • Two-way traffic is being maintained during work hour by using temporary signals.
  • The contractor is constructing new storm sewers, culverts and earth embankment for the proposed Crocker Road Extension from Lorain Road to Center Ridge Road.
  • Earth moving operation and Biddulf ditch relocation is in progress.
  • Temporary pavement construction will begin this week on Stearns from I-480 to Lorain Road.
  • After the installation of the temporary pavement, two-way traffic will be diverted to the west side of the roadway for construction of the new pavement.
  • In August, traffic will be shifted onto temporary pavement along the north side of Lorain Road for the construction of new pavement on the south side.
  • New pavement construction will begin on Stearns Road mid-July and on the south side of Lorain Road in August.

 

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Monday, August 6, 2007

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • All sewer and water work and box culvert placement is completed on Stearns from I-480 to Lorain Road.
  • Temporary pavement is placed on the west side of Stearns.
  • Two-way traffic is being maintained during work hours by use of temporary signals and/or flagmen.
  • Existing 12" water main lowering in progress on Lorain Road west and east of Stearns.
  • New storm sewer trunk line and crossovers are being constructed for the proposed roadway. Trunk line to be completed this week with the crossovers completed in two weeks.
  • On August 13, 2007, two-way traffic will be diverted to the west side of the roadway from I-480 to Lorain.
  • In mid-August, traffic will be shifted onto temporary pavement along the north side of Lorain Road for construction of new pavement on the south side. Two-way traffic will be maintained.
  • The proposed sound walls are scheduled to be installed during winter months.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Friday, May 9, 2008

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • On Tuesday, May 13, 2008, Stearns Road will close between I-480 to Lorain Road in the City of North Olmsted. The closure will begin at 6:30 a.m. and will only last the day.
  • Roadway will be closed to thru traffic, however emergency vehicles and local residents will be granted entry.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Tuesday, August 12, 2008

NOTICE TO PROCEED

  • March 1, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

Currently construction the Stearns Road/Lorain Road intersection.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Monday, October 6, 2008

NOTICE TO PROCEED

  • March 15, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • Currently working on the construction of the Crocker Road/Center Ridge Road Intersection. Will continue for the next couple of weeks.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

  • Friday, November 7, 2008

NOTICE TO PROCEED

  • March 15, 2007

COMPLETION DATE

  • September 1, 2009

PROJECT AMOUNT

  • $13,299,797.20

PROGRESS

  • Continuing work on the Crocker Road/Center Ridge Road intersection.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

Thursday, December 4, 2008

NOTICE TO PROCEED

March 15, 2007

COMPLETION DATE

September 1, 2009

PROJECT AMOUNT

$13,299,797.20

PROGRESS

  • Currently constructing the Crocker Road-Stearns Road intersections.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

Monday, December 8, 2008

NOTICE TO PROCEED

March 15, 2007

COMPLETION DATE

September 1, 2009

PROJECT AMOUNT

$13,299,797.20

PROGRESS

  • A ribbon cutting ceremony for this extension project will take place on Thursday, December 18, 2008 at the City of North Olmsted & City of Westlake border line on the new roadway. This event will begin at 10:30 a.m.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

May 22, 2009

NOTICE TO PROCEED

March 15, 2007

COMPLETION DATE

September 1, 2009

PROJECT AMOUNT

$13,299,797.20

PROGRESS

  • On Tuesday, May 26, 2009, construction will commence on the Center Ridge Road/Crocker Road intersection.
  • Two-way traffic will be maintained on both Center Ridge Road and Crocker Road. There will be no turn lanes for southbound traffic onto Crocker Road. Traffic congestion is likely.

 

 