[ Cuyahoga County Engineer's Seal ]


Organizational Duties Project Planning & Funding Department Directory News Releases Traffic Count Data Aerial Photo Price List Public Information Services Civil Engineering Co-operative Education Program Office History Leave us an e-mail


Home

The Cuyahoga County Engineer's Office

Construction Projects Update

 


 

CONSTRUCTION PROJECT UPDATE

Bainbridge Road Grading, Drainage & Paving

S.O.M. Center Road to the Solon East Corporation Line

City of Solon

DATE:

September 1, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 2010.

COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

 

  • Pre-phase sections (S.O.M. Center Road to City Hall) complete and open to traffic as per plan.
  • Underground utilities complete from S.O.M. Center Road to Huntington Drive, temporary road complete and in service from City Hall (STA 10x50 RT) to east of Huntington Drive (STA 41x00 RT).
  • Continued installation of 13’ x 5’ precast concrete box culvert at N. /S. Huntington Drive.

 

CONSTRUCTION PROJECT UPDATE

Bainbridge Road Grading, Drainage & Paving

S.O.M. Center Road to the Solon East Corporation Line

City of Solon

DATE:

August 3, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 2010

.COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

    • Completion of Phases A and C.
    • Completion of proposed 12" water main from SOM Center Road to Huntington.
    • Completion of proposed storm and sanitary sewers from SOM Center Road to Huntington.
    • Continued placement of proposed 13’x5’ precast box culvert at Huntington.

       

 

CONSTRUCTION PROJECT UPDATE

Bainbridge Road Grading, Drainage & Paving

S.O.M. Center Road to the Solon East Corporation Line

City of Solon

DATE:

July 7, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 2010

COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

    • Continued installation of proposed 13’x5’ precast box culvert at S. Huntington.  
    • Continued installation of proposed storm sewers and catch basins in Section l.
    • Placement of concrete curb and asphalt in Phase A.

 

 

 

 

                   CONSTRUCTION PROJECT UPDATE


               Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line City of Solon

DATE:

June 1, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 2010

COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

 Continue installation of catch basins and storm sewers,
chlorination of proposed 12” water main in Phase A.
 Beginning construction of the Huntington Culvert.
 

 

 

 

CONSTRUCTION PROJECT UPDATE

Bainbridge Road Grading, Drainage & Paving

S.O.M. Center Road to the Solon East Corporation Line

City of Solon

DATE:

April 12, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 1010

COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

  • Week of April 5, 2010
  • Completion of temporary road in Phase A.
  • Installation of temporary signal at Route 91.

 

 

 

CONSTRUCTION PROJECT UPDATE

Bainbridge Road Grading, Drainage & Paving

S.O.M. Center Road to the Solon East Corporation Line

City of Solon

DATE:

April 2, 2010

NOTICE TO PROCEED

March 1, 2010

START DATE

April 5, 1010

COMPLETION DATE

June 2012

PROJECT AMOUNT

$11,983,998.67

PROGRESS

  • Project will begin on Monday, April 5, 2010.
  • Work will consist of reconstructing approximately 2.44 miles of  Bainbridge Rd.
  • New flexible pavement with concrete curb, new closed drainage system Along with Traffic signals and integral bike lanes.
  • Traffic will be maintained at all times throughout the course of this project.

 

 

 

 

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Wednesday, September 01, 2010.

© 1999-2010 Cuyahoga County Engineer's Office