Construction Projects Update
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line
City of Solon
DATE:
September 1, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 2010.
COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Pre-phase sections (S.O.M. Center Road to City Hall)
complete and open to traffic as per plan.
Underground utilities complete from S.O.M. Center Road to
Huntington Drive, temporary road complete and in service from City
Hall (STA 10x50 RT) to east of Huntington Drive (STA 41x00 RT).
Continued installation of 13’ x 5’ precast concrete box culvert at
N. /S. Huntington Drive.
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line
City of Solon
DATE:
August 3, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 2010
. COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Completion of Phases A and C.
Completion of proposed 12" water main from SOM
Center Road to Huntington.
Completion of proposed storm and sanitary sewers from
SOM Center Road to Huntington.
Continued placement of proposed 13’x5’ precast box culvert
at Huntington.
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line
City of Solon
DATE:
July 7, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 2010
COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Continued installation of proposed 13’x5’ precast box culvert
at
S. Huntington.
Continued installation of proposed storm sewers and catch
basins in Section l.
Placement of concrete curb and asphalt in Phase A.
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line City of Solon
DATE:
June 1, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 2010
COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Continue installation of catch basins and storm sewers,
chlorination of proposed 12” water main in Phase A.
Beginning construction of the Huntington Culvert.
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line
City of Solon
DATE:
April 12, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 1010
COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Week of April 5, 2010
- Completion of temporary road in Phase A.
- Installation of temporary signal at Route 91.
CONSTRUCTION PROJECT UPDATE
Bainbridge Road Grading, Drainage & Paving
S.O.M. Center Road to the Solon East Corporation Line
City of Solon
DATE:
April 2, 2010
NOTICE TO PROCEED
March 1, 2010
START DATE
April 5, 1010
COMPLETION DATE
June 2012
PROJECT AMOUNT
$11,983,998.67
PROGRESS
Project will begin on Monday, April 5, 2010.
Work will consist of reconstructing approximately 2.44 miles of
Bainbridge Rd.
New flexible pavement with concrete curb, new closed drainage system
Along with Traffic signals and integral bike lanes.
- Traffic will be maintained at all times throughout the course of
this project.