WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Thursday, May 10, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

PROGRESS

  • Contractor will move on site on Monday, May 15, 2007.
  • Traffic will be maintained at all times, but delays are to be expected.

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Tuesday, June 19, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

PROGRESS

  • Saw cutting for full depth pavement removal and replacement is completed.
  • Areas of old concrete were being pulled for replacement
  • Areas are being prepared for 9’ reinforced concrete placement.
  • Northbound curb lane is closed from Center Ridge to Swartz Road.
  • Operation will continue north to Hilliard Road this week.

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Monday, July 16, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

PROGRESS

  • Catch basin adjustments and reconstruction have been completed.
  • All partial depth repairs have been completed.
  • The contractor will start crack sealing, cutting butt joints and diamond blade grinding of the gutter the week of July 15, 2007.
  • The intermediate asphalt course will begin on Friday, July 20, 2007.

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Monday, August 6, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

PROGRESS

  • The intermediate asphalt has been placed.
  • Curb ramps, manhole and valve box adjustments are being excavated. Concrete is being placed.
  • Loop detectors were to be placed on August 4th and 5th.

The surface course asphalt is scheduled for August 7th

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Monday, August 20, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

CONTRACTOR

    • Karvo Paving Company

PROGRESS

  • Asphalt, curb ramps and sidewalk have been placed and completed.
  • Saw cutting and sealing of transverse joints is set to begin.
  • Temporary striping has been placed and roadway has been opened.
  • Permanent striping will be placed after the saw cutting and the rejuvenating agent is placed on the surface course of the roadway.
  • During these operations, lanes will be closed.
  • Seed and mulch will be placed.

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Monday, August 25, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

CONTRACTOR

    • Karvo Paving Company

PROGRESS

  • Traffic is being maintained in two lanes with barrels, signage and message boards.
  • Expansion and contraction joints are being cut and sealed.
  • By September 5th, a rejuvenating agent will be applied to the surface and permanent striping will be completed.
  • Landscaping and concrete items are complete.

 

WEEKLY PROJECT UPDATE

CROCKER ROAD RESURFACING

HILLIARD BLVD. TO CENTER RIDGE ROAD

WESTLAKE

 

DATE

  • Friday, September 28, 2007

NOTICE TO PROCEED

  • May 8, 2007

START DATE

  • May 15, 2007

COMPLETION DATE

  • September 9, 2007

PROJECT AMOUNT

  • $1,243,631.00

CONTRACTOR

    • Karvo Paving Company

PROGRESS

  • Roadway is open to traffic and complete.

 

 