WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Thursday, May 10, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
PROGRESS
Contractor will move on site on Monday, May 15, 2007.
Traffic will be maintained at all times, but delays are to be
expected.
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Tuesday, June 19, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
PROGRESS
Saw cutting for full depth pavement removal and replacement is
completed.
Areas of old concrete were being pulled for replacement
Areas are being prepared for 9’ reinforced concrete placement.
Northbound curb lane is closed from Center Ridge to Swartz Road.
Operation will continue north to Hilliard Road this week.
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Monday, July 16, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
PROGRESS
Catch basin adjustments and reconstruction have been completed.
All partial depth repairs have been completed.
The contractor will start crack sealing, cutting butt joints and
diamond blade grinding of the gutter the week of July 15, 2007.
The intermediate asphalt course will begin on Friday, July 20, 2007.
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Monday, August 6, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
PROGRESS
The intermediate asphalt has been placed.
Curb ramps, manhole and valve box adjustments are being excavated.
Concrete is being placed.
Loop detectors were to be placed on August 4th and 5th.
The surface course asphalt is scheduled for August 7th
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Monday, August 20, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
CONTRACTOR
Karvo Paving Company
PROGRESS
Asphalt, curb ramps and sidewalk have been placed and completed.
Saw cutting and sealing of transverse joints is set to begin.
Temporary striping has been placed and roadway has been opened.
Permanent striping will be placed after the saw cutting and the
rejuvenating agent is placed on the surface course of the roadway.
During these operations, lanes will be closed.
Seed and mulch will be placed.
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Monday, August 25, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
CONTRACTOR
Karvo Paving Company
PROGRESS
Traffic is being maintained in two lanes with barrels, signage and
message boards.
Expansion and contraction joints are being cut and sealed.
By September 5th, a rejuvenating agent will be applied to
the surface and permanent striping will be completed.
Landscaping and concrete items are complete.
WEEKLY PROJECT UPDATE
CROCKER ROAD RESURFACING
HILLIARD BLVD. TO CENTER RIDGE ROAD
WESTLAKE
DATE
Friday, September 28, 2007
NOTICE TO PROCEED
May 8, 2007
START DATE
May 15, 2007
COMPLETION DATE
September 9, 2007
PROJECT AMOUNT
$1,243,631.00
CONTRACTOR
Karvo Paving Company
PROGRESS
Roadway is open to traffic and complete.