|
![[ Cuyahoga County Engineer's Seal ]](../images/small_white_logo.gif)

 |
|
The Cuyahoga County Engineer's Office
Construction Projects Update
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
July 7, 2010
NOTICE TO PROCEED
February 2008
COMPLETION DATE
August, 2011
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Section1 First Avenue to 12+020 (north of Sheldon West)
Section 2: 12+020 (north of Sheldon West) to 12+720 (SR 237)
Section 3: Bagley Road to First Avenue
PROGRESS:
- In Section 1: Stage 2 piling installation completed.
- Proposed abutment construction in progress with rear abutment footer
Complete, rear abutment wall in progress.
- Forward abutment footer placement scheduled for next week.
- Completion of abutment construction set for mid August.
- Stage 2 bridge completion set for October 2010.
- Sheldon Road slated for 2011.
- In Section 2: Complete, with punch list work to be completed.
- In Section 3: Work complete with exception of minor items and punch
list.
NOTES:
- In Section 1: Closed to thru traffic for construction of proposed
CSX Bridge.
- Eastland Road in this area will be closed to all traffic between
Sheldon Rd. East and Sheldon Rd. West for duration of CSX Bridge and
pavement construction.
- Sheldon Rd. west closed at Eastland Rd.
- In Section 2: Traffic per normal two-way traffic pattern except
Eastland Rd. is closed at south end near Sheldon West for construction
of CSX Bridge.
In Section 3: Traffic per normal two-way pattern.
- Eastland Rd. from First Avenue to Sheldon Rd. East currently open to
two-way traffic using temporary signals.
TRUCK ROUTES:
- Currently trucks can access Eastland Rd. south of CSX Bridge from
Bagley Road or Sheldon Rd. East from Engle Road.
FIRST AVENUE OPEN TO FRONT STREET, SOUTHBOUND ONLY TO BAGLEY ROAD.
- Front Street north of First Avenue is closed.
- Trucks to I-71 follow Bagley Road to Engle Road or Sheldon Rd. east
to Engle Rd. north to Snow Road.
- NO TRUCKS ON HOLLAND ROAD, POLICE WILL TICKET.
- Eastland Road north of CSX Bridge accessed only from SR 237.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT BAGLEY ROAD TO SR 237, INCLUDING THE GRADE
SEPARATION AT CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE
NO. 27 OVER ABRAMS CREEK BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
June 1, 2010
NOTICE TO PROCEED
February 2008
COMPLETION DATE
August, 2011
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Section1 First Avenue to 12+020 (north of Sheldon West)
Section 2: 12+020 (north of Sheldon West) to 12+720 (SR 237)
Section 3: Bagley Road to First Avenue
In Section 1: Demolition of old CSX Bridge No. 50 complete.
Mass excavation also complete.
Installation of sheet piling to start this week.
Bridge completion set for October of 2010.
First Avenue, Sheldon Road work slated for 2011.
In Section 2: Complete, with punch list work to be completed.
In Section 3: Work completed with exception of minor items and punch
list.
Permanent striping to be completed soon.
Section 1: Closed to thru traffic for construction of proposed CSX
Bridge.
Eastland Road in this area will be closed to all traffic between Sheldon
Road East
and Sheldon Road West for the duration of CSX Bridge and pavement
construction.
Sheldon Road West closed at Eastland Road.
Section 2: Traffic per normal two-way traffic pattern except Eastland
Road is closed
at south end near Sheldon Road West for construction of CSX Bridge.
Section 3: Traffic per normal two-way pattern.
Eastland Road from First Avenue to Sheldon Avenue to Sheldon Road East
currently
open to two-way traffic using temporary signals.
Currently trucks can access Eastland Road south of CSX Bridge from
Bagley Road or
Sheldon Road East from Engle Road.
First Avenue is open to Front Street, southbound only to Bagley Road.
Front Street north of First Avenue is closed.
Trucks to I-71 follow Bagley Road to Engle Road or Sheldon Road east to
Engle Road
north to Snow Road.
NO TRUCKS ON HOLLAND ROAD, POLICE WILL TICKET.
Eastland Road north of CSX Bridge accessed only from SR 237.
CONSTRUCTION PROJECT UPDATE
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
May 11, 2010
NOTICE TO PROCEED
February 2008
COMPLETION DATE
August, 2011
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Section1 First Avenue to 12+020 (north of Sheldon West)
Section 2: 12+020 (north of Sheldon West) to 12+720 (SR 237)
Section 3: Bagley Road to First Avenue
- In Section 1: Track switch completed per CSX.
- CSX Railroad Bridge No. 50 under construction, demolition
currently taking place
on existing structure.
- CSX Bridge completion set for late 2010.
- Section 2: Complete, with some punch list work to be completed.
- Section 3: Work completed with exception of minor items and punch
list.
- Permanent striping to be completed soon.
- Section 1: Closed to thru traffic for construction of proposed CSX
Bridge.
- Eastland Road in this area will be closed to all traffic between
Sheldon Road East
and Sheldon Road West for the duration of CSX Bridge and
pavement
construction.
- Sheldon Road West is closed at Eastland Road.
- Section 2: Normal two-way traffic pattern except Eastland Road is
closed at
south end near Sheldon West for construction of CSX Bridge.
- Section 3: Normal two-way traffic pattern.
- Eastland Road from First Avenue to Sheldon East currently open to
two-way
traffic using temporary signals.
First Avenue is now open to Depot Street and Bagley south.
Front Street north of First Avenue is closed.
Truck Routes: Currently trucks can access Eastland Road south of
CSX Bridge
from Bagley Road or Sheldon East from Engle Road.
- First Avenue open to Front Street, southbound only to Bagley Road.
- Front Street north of First Avenue is closed.
- Trucks to I-71 follow Bagley Road to Engle Road or Sheldon Road
east to
Engle Road north to Snow Road.
- NO TRUCKS ON HOLLAND ROAD, POLICE WILL TICKET.
- Eastland Road north of CSX Bridge accessed only from SR 237.
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
March 9, 2010
NOTICE TO PROCEED
February 2008
COMPLETION DATE
August, 2011
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Section1 First Avenue to 12+020 (north of Sheldon West)
Section 2: 12+020 (north of Sheldon West) to 12+720 (SR 237)
Section 3: Bagley Road to First Avenue
- In Section 1 First Avenue reconstruction to start April/May.
- CSX Railroad Bridge No. 50 on hold per track switch by CSX Railroad.
- Temporary tracks are completed.
- Remainder of work involving Sheldon Road set for summer, relevant to
progress on CSX Railroad Bridge Project on hold per CSX Railroad Bridge
work.
- In Section 2 Complete, with some punch list work to be completed.
- In section 3 Work completed with exception of minor items, permanent
striping to be completed in spring.Section 1 Closed to thru traffic for
construction of proposed CSX Railroad Bridge.
- Eastland Road in this area will be closed to all traffic between
Sheldon Road Eastand Sheldon Road West for the duration of CSX Railroad
Bridge and pavement construction.
- Sheldon Road West closed at Eastland Road.
In Section 2 Normal two-way traffic pattern except Eastland Road is
closed at the south end near Sheldon Road West for construction of CSX
Railroad Bridge.
- In Section 3 Normal two-way pattern. Eastland Road from First Avenue
to Sheldon
Road East currently open to two-way traffic using temporary
signals. Same to be one lane, eastbound only when First Avenue
construction begins.
- Currently trucks can access Eastland Road south of CSX Railroad
Bridge from Bagley Road to Sheldon Road east from Engle Road.
- First Avenue is open to Front Street, southbound only to Bagley
Road.
- Front Street north of First Avenue is closed.
- Truck to I-71 follow Bagley Road to Engle Road or Sheldon Road east
to Engle Road north to Snow Road.
No trucks permitted on Holland Road, Police will Ticket.
- Eastland Road north of CSX Railroad Bridge accessed only from SR
237.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
October 27, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
May 4, 2011
PROJECT AMOUNT
$17,999,999.99
PROGRESS
T he Paving in Section 3, from Bagley Road to First Avenue is
completed.
Grading and placing of topsoil for sod placement is currently being
done.
Landscaping will begin this week. Completion for Section 3 is set for
November 2009.
Traffic in this section is one-way northbound only from Bagley Road to
Sheldon East
until November 2, 2009, after November 2, 2009, the roadway from Bagley
Road to First Avenue will be open to two-way traffic.
Eastland Road from First Avenue to Sheldon East will remain one-way
northbound only during Section 3 construction.
First Avenue is open to Depot Street and Bagley south.
Front Street north of First Avenue is closed.
Work on the CSX Railroad Bridge No. 50 in Section 1, First Avenue to
just north of Sheldon West has begun. Installation of temporary rail bed
and tracks will be completed in November 2009. The excavating, water and
sewer work are to begin in November 2009, for Sheldon West.
This section is closed to through traffic for construction of proposed
CSX Bridge No. 50. In this area, Eastland Road will be closed to all
traffic between Sheldon East and Sheldon West for the duration of the CSX
Bridge No. 50 and pavement construction.
Sheldon West is closed at Eastland Road.
Section 2, just north of Sheldon West to SR 237 is complete with the
exception of punch list work.
Two-way traffic is maintained in this area with the exception of
Eastland Road being closed at the south end near Sheldon West for CSX
Bridge construction.
Beginning November 2, 2009 trucks accessing businesses on Eastland Road
between Bagley Road and Sheldon East from Bagley Road or First Avenue as
Eastland Road will be open to two-way traffic.
First Avenue is open from Front Street, southbound only to Bagley Road.
Front Street north of First Avenue is closed.
Trucks to I-71 are to follow Sheldon Road east to Engle Road north to
Snow Road.
Trucks will not be permitted onto Holland Road. Sheldon Road between
Engle Road and Eastland Road is closed at Eastland Road.
Eastland Road cannot be accessed from Engle Road.
Eastland Road between Sheldon Road and State Route 237 can be accessed
from SR 237.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
September 3, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
On Friday, September 4, 2009, a new traffic pattern will take place. At
7:00 a.m., Eastland Road will be one-way northbound from First Avenue and
Sheldon Road will be one-way eastbound. Detours will be posted. This
traffic pattern is necessary in order to construct the new railroad bridge
over the Eastland Road/Sheldon Road intersection.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
August 31, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- The paving of Section 3, from Bagley Road to First Avenue is
complete with the exception of intersection work at Bonds and Robin.
Grading is currently being done for sidewalks and driveways. However,
in a few areas, water, sewer and electrical work are left. Landscaping
will begin in mid-September and will last till October. This section
will be completed in November 2009.
- Traffic in this section is one-way northbound only from Bagley
Road to Sheldon East until construction is complete in this section.
Eastland Road, from First Avenue to Sheldon East, is open to two-way
traffic during Section 3 construction.
- Work on the CSX Railroad Bridge No. 50 in Section 1, First Avenue
to just north of Sheldon West, has begun. Currently in progress is the
installation of necessary items for the temporary railroad. The
excavation, water and sewer work are on hold for Sheldon Road.
- This section is closed to thru traffic for construction of the
proposed CSX Bridge No. 50. In this area, Eastland Road will be closed
to all traffic between Sheldon East and Sheldon West for the duration
of the CSX Bridge construction. Sheldon West is closed at Eastland.
- Section 2, just north of Sheldon West to SR 237, is complete with
the exception of punch list work. Landscaping is almost complete.
- Two-way traffic is maintained in this area, with the exception of
Eastland Road being closed at the south end near Sheldon West for the
CSX Bridge construction. First Avenue is open to Depot Street and
Bagley south. Front Street north of First Avenue is closed.
- Trucks accessing businesses on Eastland Road between Bagley Road
and First Avenue, must enter from Bagley Road only.
- Trucks can access businesses between First Avenue and Sheldon East
from either Bagley Road or Sheldon East via Engle Road.
- Trucks to I-71 are to follow Sheldon east to Engle north to Snow
Road.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
August 11, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- On Thrusday, August 13, 2009, the northbound lane of Eastland Road
will be paved from Brookstone Trail to First Avenue, weather
permitting. Work is scheduled to begin at approximately 7:00 a.m. and
is expected to conclude at 6:00 p.m. Long delays are to be expected.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
July 21, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- Section 3 (Bagley Road to First Avenue) is complete with the
exception of the sidewalk, residential drives and landscaping. The storm
sewer work in Phase B (on the east side of the roadway) is nearly
complete. Existing pavement has been removed and work is underway to
place proposed intersections. Section 3 is scheduled for completion on
October 1, 2009. Currently, traffic in this section is one-way
northbound from Bagley Road to Sheldon East for Phase B pavement
construction. However, Eastland Road is open to two-way traffic from
First Avenue to Sheldon East.
- Section 1(First Avenue to just north of Sheldon West) work on CSX
Bridge No. 50 is expected to start in mid-August. In addition,
excavation and water & sewer work is underway on Sheldon West. Section 1
is closed to thru traffic for construction of proposed CSX Bridge No.
50. Eastland Road will be closed to all traffic between Sheldon East and
Sheldon West in this area for the duration of the bridge construction.
Sheldon is currently closed at Eastland.
- Section 2 (just north of Sheldon West to SR 237) is nearly complete
with the exception of minor work. Landscaping is nearly complete in this
section. In this section, traffic is two-way with the exception of
Eastland being closed at the south end near Sheldon West for the
construction of CSX Bridge No. 50.
- Note:
- Trucks must access businesses on Eastland Road between Bagley and
First Avenue from Bagley Road only.
- Trucks can access businesses between First Avenue and Sheldon East
from either Bagley Road or Sheldon East via Engle Road.
- Southbound traffic will be prohibited at First Avenue. Truck to
I-71 should follow Sheldon east to Engle north to Show Road. First
Avenue is closed at Front Street per ODOT’s Front Street project. This
is expected to re-open August 1st. Once open, two-way
traffic from First Avenue to Bagley Road will be allowed on Front
Street. However, Front Street north of First Avenue will remain
closed.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
June 10, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- On Saturday, June 13, 2009, the center lane of Eastland Road from
Brookstone Trail to First Avenue will be paved, weather permitting. The
southbound turning lane on Eastland Road at Bagley Road will also be
paved.
- Paving will begin at 7:00 a.m. and will be completed by
approximately 6:00 p.m.
- During the paving process, Eastland Road will be closed at Bagley
Road, with the exception of residents. All other traffic will be
detoured via Engle Road to Sheldon Road or Front Street To First Avenue.
CONSTRUCTION PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
June 4, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- On June 6, 2009, the southbound curb lane of Eastland Road will be
paved from Williamsburg Court to First Avenue. The work will begin at
approximately 7:00 a.m. and will conclude at 6:00 p.m., weather
permitting.
- During this operation, Eastland Road will be closed at Bagley Road,
except for residents. All other traffic will be detoured via Engle Road
to Sheldon Road or Front Street to First Avenue. Police will be
directing traffic throughout the entire work day. Major traffic delays
are expected.
PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
May 27, 2009 ** UPDATED
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- On May 30, 2009, the southbound curb lane of Eastland Road will be
paved from Bagley Road to Brookstone Trail. The work will begin at
approximately 7:00 a.m. and will conclude at 6:00 p.m., weather
permitting.
- Residents of Williamsburg Court will be affected by this work.
During work hours, upon leaving their residence, they must use Eastland
Road northbound. Upon arriving back home, they must use First Avenue.
Police will be on hand to direct traffic throughout the course of the
work day. Major delays are to be expected.
PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
May 27, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- On May 30, 2009, the southbound curb lane of Eastland Road will be
paved from Bagley Road to Brookstone Trail. The work will begin at
approximately 7:00 a.m. and will conclude at 6:00 p.m., weather
permitting.
- At this time, traffic will be closed to all motorists at Bagley
Road, except for residents. All other traffic must use the following
roads: Engle Road to Sheldon Road or Front Street to First Avenue.
PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
May 4, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Section 1: First Avenue to just north of Sheldon West
Section 2: Just north of Sheldon West to SR 237
Section 3: Bagley Road to First Avenue
- Storm sewers and water work items have been completed in Section 3.
Eastland Road is one-way traffic northbound from Bagley Road to First
Avenue for pavement construction. Southbound traffic is detoured. During
this time, Eastland Road, from First Avenue to Sheldon East, is open to
two-way traffic. During this time, any truck that must access a
business on Eastland Road, between Bagley Road and First Avenue, will be
able to enter from Bagley Road only.
Southbound traffic will be prohibited at First Avenue. Trucks
needing to access I-71 should follow Sheldon East to Engle North to
Snow Road.
- Work in Section 1 on the CSX Railroad Bridge No. 50 has been delayed
and will begin in June 2009. When work commences on the bridge, Eastland
Road will be closed to all traffic between Sheldon East and Sheldon West
for the duration of the bridge construction.Work in this section on
water, sewer and excavation involving Sheldon West will begin in May
2009.
- Section 2 is almost completed with the exception of landscaping and
minor work. Landscaping is to start the week of May 4th.
PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
April 7, 2009
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- Storm sewers and water work items are currently being installed from
Bagley Road to First Avenue. This work is scheduled for completion in
mid-April.
- Pavement construction from Bagley Road to First Avenue is set to
start April 13.
- Work on the CSX Bridge #50 is currently set to start at the end of
April. This is closed to thru traffic for construction of the bridge.
- Eastland Road from just north of Sheldon West and SR 237 is nearly
complete.
- Currently, two-way traffic is being maintained during work hours
using flagmen from Bagley Road to First Avenue. However, on Monday,
April 13, 2009, traffic in this area will be one-way northbound only
from Bagley Road to Sheldon East for pavement construction on the west
side of the roadway. Southbound motorists will be detoured. During this
period, Eastland Road from First Avenue to Sheldon East will be open to
two-way traffic.
- During this time, any truck that must access a business on Eastland
Road, between Bagley Road and First Avenue, will be able to enter from
Bagley Road only.
- Southbound traffic will be prohibited at First Avenue. Trucks
needing to access I-71 should follow Sheldon East to Engle North to Snow
Road.
PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
Wednesday, October 15, 2008
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
- The contractor will finish placing reinforced concrete pavement on
the left side of Eastland Road between Sheldon Road and SR 237 the week
of 10/13-10/17. All castings will be adjusted in the roadway to grade in
the same locations.
- Catch basins and exfiltration trenches will be set during the week f
10/20-10/24.
- Topsoil will be placed in all areas that have been disturbed where
reinforced concrete pavement, drive aprons and sidewalk have been
placed.
- On Friday, October 31, 2008, Eastland Road, from the north side of
Sheldon Road, will be opened to two-way traffic. Once this pavement has
been opened, the Sheldon Road and Eastland Road intersection will be
closed to all traffic. This closure will last for a period of 18 months
to perform section 1 of this project. Any traffic that will be required
to travel on Eastland Road north of Sheldon Road must enter from either
SR 237 or Holland Road.
PROJECT UPDATE
EDDY ROAD REPAIR & RESURFACING
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
Thursday, September 18, 2008
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
The contractor will be completing the 260mm reinforced concrete
pavement on the right side of Eastland Road from north of Sheldon Road
to just south of the Norfolk Southern Railroad tracks at SR 237.
The placement of concrete for all drive aprons on the right side of
Eastland Road will be completed this week.
The installation of the precast arch culvert over Abram Creek is
complete.
Northbound traffic on Eastland Road north of Sheldon Road will be
switched onto the new pavement on Monday, September 22, 2008.
Concrete pavement on the left side of Eastland Road is scheduled to
be completed by the end of October 2008.
Once paved, Eastland Road will be open to two-way traffic, the
Eastland Road and Sheldon Road intersection will be closed to all
traffic. At that time, the contractor will resume work on the
replacement and realignment of the CSX Railroad Bridge No. 50R at that
intersection.
Two-way traffic south of Sheldon is being maintained.
WEEKLY PROJECT UPDATE
EASTLAND ROAD IMPROVEMENT
BAGLEY ROAD TO SR 237, INCLUDING THE GRADE SEPARATION AT
CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE NO. 27 OVER
ABRAMS CREEK
BEREA, BROOK PARK & MIDDLEBURG HEIGHTS
DATE
Thursday, February 7, 2008
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Project will begin on Monday, February 11, 2008.
Work will begin on Section 2, which consists of the area of Eastland
just north of Sheldon Road to S.R. 237.
Traffic will be maintained one-way northbound between Sheldon Road
and S.R. 237. Southbound traffic will use the following detour: S.R. 237
to Sheldon Road to Eastland Road.
To View A detour map in PDF Format
Click Here.
WEEKLY PROJECT UPDATE:
EASTLAND ROAD IMPROVEMENT BAGLEY ROAD TO SR 237, INCLUDING THE GRADE
SEPARATION AT CONRAIL RAILROAD AND THE REPLACEMENT OF EASTLAND ROAD BRIDGE
NO. 27 OVER ABRAMS CREEK BEREA, BROOK PARK & MIDDLEBURG HEIGHTS.
DATE:
Tuesday, January 15, 2008
NOTICE TO PROCEED
February 2008
COMPLETION DATE
October 2010
PROJECT AMOUNT
$17,999,999.99
PROGRESS
Public meeting for this project will be held on:
Thursday, January 31, 2008 7:00 p.m.
Doors open at 6:30 p.m.
Berea High School
165 E. Bagley Road
Representatives from the Cuyahoga County Engineer’s Office, Cities of
Berea, Brook Park & Middleburg Heights and Anthony Allega Cement
Contractor will be present.
This page has been accessed times
since February 26, 2004
and was last updated on
Thursday, July 08, 2010.
© 1999-2008 Cuyahoga County Engineer's Office |