WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Thursday, March 29, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
October 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Concrete barrier wall sections have been placed blocking the north
side of the bridge and roadway.
Two-way traffic, with one lane in each direction, in the south lane.
Removal operations have begun on the left side parapet and deck.
FUTURE
April 2-April 16: Approach slab, deck and abutment removals
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Friday, April 13, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
The 32" concrete barrier wall sections have been placed, blocking
the north side of the bridge and roadway.
Two-way traffic, with one lane in each direction, is being
maintained in the south lane by four signal heads.
Left Pier modification work is in progress.
Anticipated work for April 16, 2007 to April 30, 2007, includes
completion of the left pier modification and the removal of the left
side bridge deck and beams.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, April 23, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
On Thursday, April 26, 2007, Harvard Road Bridge No. 82 will be
closed for the day to all traffic. Detour routes will be established.
Bridge will reopen the following day.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Thursday, May 3, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Sections of a 32" concrete barrier wall have been placed blocking
the north side of the bridge and roadway.
Two-way traffic, with one lane in each direction, is being
maintained in the south lane by four signal heads.
Left side beams have been removed between the pier and forward
abutment.
Anticipated work for May 1, 2007 to May 15, 2007 includes deck, beam
and forward abutment removal.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Wednesday, May 23, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Concrete barrier wall sections have been placed, blocking the north
side of the bridge and roadway.
Two-way traffic, with one lane in each direction, is being
maintained in the southbound lanes.
The reconstruction of the forward and rear abutments is in progress
on the left side.
Anticipated work from May 16 through May 31 includes the completion
of the left rear and forward abutment operations.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Tuesday, June 19, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
32" concrete barrier wall sections have been placed blocking the
north side of the bridge and roadway.
Two-way traffic is being maintained in the south lane by use of
signal heads.
Anticipated work from June 16, 2007 through June 30, 2007 includes
performance of left rear and forward wing wall construction and sections
of the existing left rear and forward abutments will be patched.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Tuesday, July 3, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
32" concrete barrier wall sections have been placed blocking the
north side of the bridge and roadway.
Two-way traffic is being maintained in the south lane by use of
signal heads.
The forward and rear abutment modifications on the left side remain
in progress.
Anticipated work from July 1, 2007 through July 15, 2007 includes
the completion of the left forward and rear abutments patching and the
placement of the left forward wing wall extension.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, August 6, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Forward and rear abutment patching has been completed.
Work operations have been suspended since July 9, 2007 and are
scheduled to resume on Monday, August 6, 2007.
Work scheduled from August 6th-August 16th
includes the left forward wing wall extension, the left forward headwall
modification and the beginning of beam placements.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Tuesday, October 2, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Beams and bracing have been placed on the left side of the bridge.
Additional forward retaining wall and wing wall sections have been
construction on the left side of the bridge.
The south side of the bridge (right side) remains open to two-lane
traffic.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, November 5, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
The left Dominion gas line assembly has been erected and the 16"
energized gas line has been placed.
The left side false deck and forming are in progress.
Projected work for the next two weeks: the completion of forming and
Rebar installation for the left forward integral abutment and the left
bridge deck.
The south two lanes of the bridge remain open to traffic.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Wednesday, December 5, 2007
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
December 11, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
The AT&T duct line on the left side of the bridge has been
connected.
The bridge deck support system on the left side has been erected and
deck framing has been completed.
Work expected for the next two weeks:
- Bridge deck re-steel installation
- Concrete placement on the left side of the bridge deck
- The south side of the bridge remains open to two-way traffic.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Friday, January 4, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2007
PROJECT AMOUNT
$1,227,414.30
PROGRESS
The left approach slabs have been completed.
During the next two weeks, the placement of 10" concrete pavement
at both the left rear and left forward roadway sides abutting the
approach slabs should be completed.
Left parapet construction should be completed.
Large chuckholes have been repaired with concrete in the right
traffic lane.
The south lanes remain open to two-way traffic.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Tuesday, February 26, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2008
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Construction on the left parapet of the bridge has been completed.
Phase II work and traffic zone change has been implemented.
Two-way traffic will be maintained on the north side of the bridge.
Some traffic delays are to be expected.
Demolition of the right bridge deck has begun
The removal of the right beam and right side pier work is
scheduled to begin on Monday, March 3, 2008.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Friday, March 14, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2008
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Phase II project work has begun
The bridge deck and parapet on the right side has been removed.
Work for the next two weeks includes the demolition and
reconstruction of the right side abutment, scaffolding erection and
pier modification.
Two-way traffic is being maintained in the north lane.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, May 5, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2008
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Phase II project work is in progress.
Ongoing construction on both abutments on the right side of
bridge.
Projected work for the next two weeks:
- Construction of the right forward abutment diaphragm
- Construction on the right rear abutment diaphragm
- Placement on the right side of deck
- Pier column modifications on the right side
- Traffic is maintained by way of work zone traffic signals.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, May 19, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2008
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Phase II project work is in progress.
- Both right side integral abutments have been constructed.
- The right side bridge deck is being placed and set to grade.
- Expected work over the next two weeks:
- Modification of the right pier column
- Construction of the right side approach slabs
- Installation of the right bridge deck stud and reinforcement
steal
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Tuesday, June 3, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
June 15, 2008
PROJECT AMOUNT
$1,227,414.30
PROGRESS
Phase 2 work is in progress
The right pier column modification is complete.
The forming of the right side bridge deck is complete.
The right side beam studs have been installed.
Expected work over the next two weeks includes:
- The placement of the right side wing walls.
- The installation of the right side deck reinforcement steel.
- The placement of the right side HP concrete deck.
WEEKLY PROJECT UPDATE
HARVARD ROAD BRIDGE NO. 82
OVER CUYAHOGA RIVER
CLEVELAND & CUYAHOGA HEIGHTS
DATE
Monday, July 7, 2008
NOTICE TO PROCEED
February 19, 2007
START DATE
March 12, 2007
COMPLETION DATE
August 8, 2008
PROJECT AMOUNT
$1,420,635.02
PROGRESS
The right forward and rear approach slabs were placed and wing
walls were placed.
The right parapet was placed.
The right deck sidewalk had IIP concrete placed.
Work for the next two weeks:
- Phase 3 operations are being implemented.
- There will be a deck closure for concrete placement.
The right side drainage conduit will be installed