CONSTRUCTION PROJECT UPDATE
LEWIS ROAD BRIDGE NO. 21 REPLACEMENT
OVER BRANCH TO THE ROCKY RIVER
NORTH OLMSTED & OLMSTED TOWNSHIP
DATE:
Wednesday, October 8, 2008
NOTICE TO PROCEED
June 2, 2008
COMPLETION DATE
August 4, 2009
PROJECT AMOUNT
$1,604,072.96
PROGRESS
The backfilling of wing walls have all been completed. The placement
of rock channel protection and painting of abutment walls have begun.
Will continue to work on rock channel protections, painting of
abutment walls and placement of concrete for backwalls.
The pre-engineered bridge/structure will tentatively arrive on
October 15, 2008.
The road remains closed and a detour route is in place.
CONSTRUCTION PROJECT UPDATE
LEWIS ROAD BRIDGE NO. 21 REPLACEMENT
OVER BRANCH TO THE ROCKY RIVER
NORTH OLMSTED & OLMSTED TOWNSHIP
DATE:
May 15, 2009
NOTICE TO PROCEED
June 2, 2008
COMPLETED
May 14, 2009
PROJECT AMOUNT
$1,604,072.96
PROGRESS
The bridge was opened to vehicle traffic at approximately 9:00 a.m.
on Thursday, May 14, 2009.
The final landscaping and signage reinstallation have been
completed.
Project is complete.
This page has been accessed times
since February 26, 2004
and was last updated on
Friday, May 15, 2009.