The Cuyahoga County Engineer's OfficeConstruction Projects Update
CONSTRUCTION PROJECT UPDATE ROCKSIDE ROAD BRIDGE NO. 218 REPLACEMENT OVER THE OHIO CANAL VALLEY VIEW DATE July 16, 2010 NOTICE TO PROCEED January 12, 2009 START DATE January 12, 2009 COMPLETION DATE July 9, 2010 PROJECT AMOUNT $1,984,441.90 PROGRESS
CONSTRUCTION PROJECT UPDATE ROCKSIDE ROAD BRIDGE NO. 218 REPLACEMENT OVER THE OHIO CANAL VALLEY VIEW DATE April 1, 2010 NOTICE TO PROCEED January 12, 2009 START DATE January 12, 2009 COMPLETION DATE July 9, 2010 PROJECT AMOUNT $1,984,441.90 PROGRESS
for the north-west abutment and wing wall sections. a tentative time extension of 3 months due to start-up delays and lost days due to weather.
CONSTRUCTION PROJECT UPDATE ROCKSIDE ROAD BRIDGE NO. 218 REPLACEMENT OVER THE OHIO CANAL VALLEY VIEW DATE October 19, 2009 NOTICE TO PROCEED January 12, 2009 START DATE January 12, 2009 COMPLETION DATE July 9, 2010 PROJECT AMOUNT $1,984,441.90 PROGRESS
to the south half of the bridge.
CONSTRUCTION PROJECT UPDATE ROCKSIDE ROAD BRIDGE NO. 218 REPLACEMENT OVER THE OHIO CANAL VALLEY VIEW DATE July 30, 2009 NOTICE TO PROCEED January 12, 2009 START DATE January 12, 2009 COMPLETION DATE July 9, 2010 PROJECT AMOUNT $1,984,441.90 PROGRESS
CONSTRUCTION PROJECT UPDATE ROCKSIDE ROAD BRIDGE NO. 218 REPLACEMENT OVER THE OHIO CANAL VALLEY VIEW DATE June 18, 2010 NOTICE TO PROCEED January 12, 2009 START DATE January 12, 2009 COMPLETION DATE July 9, 2010 PROJECT AMOUNT $1,984,441.90 PROGRESS pavement, curb and catch-basin installation.
Blaze Construction Company for weather and construction related delays.