Construction Projects Update
CONSTRUCTION PROJECT UPDATE
ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING
E. 72ND STREET TO E. 140TH STREET
CLEVELAND
DATE
November 3, 2009
NOTICE TO PROCEED
April 27, 2009
START DATE
April 27, 2009
COMPLETION DATE
October 13, 2010
PROJECT AMOUNT
$8,026,384.53
CONTRACTOR
Terrace Construction Company, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and
Cleveland
PROGRESS
- St. Clair Avenue is completely open to traffic from E. 72nd
Street through E.125th Street.
- Section 3 Phase A, north side of St. Clair Avenue from E.115th
Street to E.140th Street concrete walk and curb work is 80%
completed.
- Signalization Conduit installations have been completed.
- Dominion Gas line repair work is ongoing between E. 88th
Street and E. 100th Street.
- Work for the next two weeks:
- Section 3 Phase A: E. 125th Street to E.140th
Street north side of St. Clair Avenue is to have concrete sidewalks
& driveway aprons placed and landscaping operations performed.
- Surface Course Asphalt paving is projected to be performed
between November 9th and November 13, 2009.
CONSTRUCTION PROJECT UPDATE
ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING
E. 72ND STREET TO E. 140TH STREET
CLEVELAND
DATE
October 5, 2009
NOTICE TO PROCEED
April 27, 2009
START DATE
April 27, 2009
COMPLETION DATE
October 13, 2010
PROJECT AMOUNT
$8,026,384.53
CONTRACTOR
Terrace Construction Company, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and
Cleveland
PROGRESS
Traffic has been completely opened in Section 1 from E.
72nd street to East 88th street on the south and north sides of roadway,
minimal pavement markings have been completed.
The surface course asphalt has been paved in Section 3, Phase A, from E.
110th Street to E.125th Street on the north side of the roadway.
The north side of Section 3 Phase A from E. 125th Street to E. 140th
Street is 66% completed.
Traffic is being maintained on the south side of St. Clair from E.110th
Street to E. 140th Street, while work is being done on north side of
roadway.
Dominion Gas line removal will be ongoing from the north side of St.
Clair Avenue between E.88th Street to E.100th street.
Work for the next two weeks:
Section 3 Phase A: Placement of sidewalks and driveway aprons
fromE.125th Street to E.140th Street on the north side of roadway
Roadway casting adjusted to grade along with landscaping performed
CONSTRUCTION PROJECT UPDATE
ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING
E. 72ND STREET TO E. 140TH STREET
CLEVELAND
DATE
September 2, 2009
NOTICE TO PROCEED
April 27, 2009
START DATE
April 27, 2009
COMPLETION DATE
October 13, 2010
PROJECT AMOUNT
$8,026,384.53
CONTRACTOR
Terrace Construction Company, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and
Cleveland
PROGRESS
- Work in Section I Phase A, from E. 72nd Street to E. 88th
Street on the north side of the street, will be completed in two weeks
(approximately September 15, 2009).
- The intermediate course asphalt has been paved in Section 3, Phase
A, from E. 125th Street to E. 140th Street on
the north side of the roadway.
- The north side of Section 3 Phase A, from E. 110th
Street to E. 125th Street is 50% complete.
- Traffic is being maintained on the south side of St. Clair in the
Phase A work zone.
- Dominion gas line removal is taking place between E. 88th
Street and E. 100th Street on both sides of the roadway.
- Work for the next two weeks:
- Section 1 Phase A: The north side of East Boulevard work will be
completed and various side street radii are to be finished.
- Section 3 Phase A: Sidewalks, curbs and driveway aprons will be
removed starting Friday, September 4, 2009 from E. 125th
Street to E. 140th Street on the north side of the
roadway.
WEEKLY PROJECT UPDATE
ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING
E. 72ND STREET TO E. 140TH STREET
CLEVELAND
DATE
June 2, 2009
NOTICE TO PROCEED
April 27, 2009
START DATE
April 27, 2009
COMPLETION DATE
October 23, 2010
PROJECT AMOUNT
$8,026,384.53
CONTRACTOR
Terrace Construction Company, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and
Cleveland
PROGRESS
Work between E. 71st Street and E. 88th St.
on Street Clair Avenue has begun. The asphalt intermediate course has
been placed.
Work between E. 110th Street and E. 141st
Street has begun. This includes pavement grinding and asphalt
intermediate course paving.
Traffic is being maintained one-way in each direction on the north
side of St. Clair Avenue.
Work for the next two weeks:
- Sidewalk placement, curb, under drain, signalization conduit
installation. Also asphalt intermediate course paving & curb & walk
removal.
Construction Projects Update
WEEKLY PROJECT UPDATE
ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING
E. 72ND STREET TO E. 140TH STREET
CLEVELAND
DATE
May 4, 2009
NOTICE TO PROCEED
April 27, 2009
START DATE
April 27, 2009
COMPLETION DATE
October 23, 2010
PROJECT AMOUNT
$8,026,384.53
CONTRACTOR
Terrace Construction Company, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and
Cleveland
PROGRESS
- Construction layout began on Monday, April 27, 2009.
- Mobilization and maintenance of traffic will be established on May
4, 2009.
- Dominion Gas will begin removing gas lines underneath sidewalk
between E. 88th Street and E. 100th Street.
This page has been accessed times
since February 26, 2004
and was last updated on
Tuesday, March 09, 2010.