Construction Projects Update

 


 

 

CONSTRUCTION PROJECT UPDATE

ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING

E. 72ND STREET TO E. 140TH STREET

CLEVELAND

DATE

November 3, 2009

NOTICE TO PROCEED

April 27, 2009

START DATE

April 27, 2009

COMPLETION DATE

October 13, 2010

PROJECT AMOUNT

$8,026,384.53

CONTRACTOR

Terrace Construction Company, Inc.

FUNDING

Federal Highway Administration through NOACA, Cuyahoga County and Cleveland

PROGRESS

    • St. Clair Avenue is completely open to traffic from E. 72nd Street through E.125th Street.
    • Section 3 Phase A, north side of St. Clair Avenue from E.115th Street to E.140th Street concrete walk and curb work is 80% completed.
    • Signalization Conduit installations have been completed.
    • Dominion Gas line repair work is ongoing between E. 88th Street and E. 100th Street.
    • Work for the next two weeks:
      • Section 3 Phase A: E. 125th Street to E.140th Street north side of St. Clair Avenue is to have concrete sidewalks & driveway aprons placed and landscaping operations performed.

       

    • Surface Course Asphalt paving is projected to be performed between November 9th and November 13, 2009.

 

 

 

CONSTRUCTION PROJECT UPDATE

ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING

E. 72ND STREET TO E. 140TH STREET

CLEVELAND

DATE

October 5, 2009

NOTICE TO PROCEED

April 27, 2009

START DATE

April 27, 2009

COMPLETION DATE

October 13, 2010

PROJECT AMOUNT

$8,026,384.53

CONTRACTOR

Terrace Construction Company, Inc.

FUNDING

Federal Highway Administration through NOACA, Cuyahoga County and Cleveland

PROGRESS

 Traffic has been completely opened in Section 1 from E. 72nd street to East 88th street on the south and north sides of roadway, minimal pavement markings have been completed.
 The surface course asphalt has been paved in Section 3, Phase A, from E. 110th Street to E.125th Street on the north side of the roadway.
 The north side of Section 3 Phase A from E. 125th Street to E. 140th Street is 66% completed.
 Traffic is being maintained on the south side of St. Clair from E.110th Street to E. 140th Street, while work is being done on north side of roadway.
 Dominion Gas line removal will be ongoing from the north side of St. Clair Avenue between E.88th Street to E.100th street.
 Work for the next two weeks:
 Section 3 Phase A: Placement of sidewalks and driveway aprons fromE.125th Street to E.140th Street on the north side of roadway
 Roadway casting adjusted to grade along with landscaping performed
 

CONSTRUCTION PROJECT UPDATE

ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING

E. 72ND STREET TO E. 140TH STREET

CLEVELAND

DATE

September 2, 2009

NOTICE TO PROCEED

April 27, 2009

START DATE

April 27, 2009

COMPLETION DATE

October 13, 2010

PROJECT AMOUNT

$8,026,384.53

CONTRACTOR

Terrace Construction Company, Inc.

FUNDING

Federal Highway Administration through NOACA, Cuyahoga County and Cleveland

PROGRESS

    • Work in Section I Phase A, from E. 72nd Street to E. 88th Street on the north side of the street, will be completed in two weeks (approximately September 15, 2009).
    • The intermediate course asphalt has been paved in Section 3, Phase A, from E. 125th Street to E. 140th Street on the north side of the roadway.
    • The north side of Section 3 Phase A, from E. 110th Street to E. 125th Street is 50% complete.
    • Traffic is being maintained on the south side of St. Clair in the Phase A work zone.
    • Dominion gas line removal is taking place between E. 88th Street and E. 100th Street on both sides of the roadway.
    • Work for the next two weeks:
      • Section 1 Phase A: The north side of East Boulevard work will be completed and various side street radii are to be finished.
      • Section 3 Phase A: Sidewalks, curbs and driveway aprons will be removed starting Friday, September 4, 2009 from E. 125th Street to E. 140th Street on the north side of the roadway.

 

 

WEEKLY PROJECT UPDATE

ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING

E. 72ND STREET TO E. 140TH STREET

CLEVELAND

DATE

June 2, 2009

NOTICE TO PROCEED

April 27, 2009

START DATE

April 27, 2009

COMPLETION DATE

October 23, 2010

PROJECT AMOUNT

$8,026,384.53

CONTRACTOR

Terrace Construction Company, Inc.

FUNDING

Federal Highway Administration through NOACA, Cuyahoga County and Cleveland

PROGRESS

    • Work between E. 71st Street and E. 88th St. on Street Clair Avenue has begun. The asphalt intermediate course has been placed.
    • Work between E. 110th Street and E. 141st Street has begun. This includes pavement grinding and asphalt intermediate course paving.
    • Traffic is being maintained one-way in each direction on the north side of St. Clair Avenue.
    • Work for the next two weeks:
      • Sidewalk placement, curb, under drain, signalization conduit installation. Also asphalt intermediate course paving & curb & walk removal.

 

Construction Projects Update

WEEKLY PROJECT UPDATE

ST. CLAIR AVENUE PHASE I REPAIR & RESURFACING

E. 72ND STREET TO E. 140TH STREET

CLEVELAND

DATE

May 4, 2009

NOTICE TO PROCEED

April 27, 2009

START DATE

April 27, 2009

COMPLETION DATE

October 23, 2010

PROJECT AMOUNT

$8,026,384.53

CONTRACTOR

Terrace Construction Company, Inc.

FUNDING

Federal Highway Administration through NOACA, Cuyahoga County and Cleveland

PROGRESS

    • Construction layout began on Monday, April 27, 2009.
    • Mobilization and maintenance of traffic will be established on May 4, 2009.
    • Dominion Gas will begin removing gas lines underneath sidewalk between E. 88th Street and E. 100th Street.

 

 

 