[ Cuyahoga County Engineer's Seal ]


Organizational Duties Project Planning & Funding Department Directory News Releases Traffic Count Data Aerial Photo Price List Public Information Services Civil Engineering Co-operative Education Program Office History Leave us an e-mail


Home

The Cuyahoga County Engineer's Office

Construction Projects Update

 


 

CONSTRUCTION PROJECT UPDATE

W. 3rd STREET BRIDGE No. 1:045

OVER THE CUYAHOGA RIVER

CITY OF CLEVELAND

DATE:

  • August 16, 2010

NOTICE TO PROCEED

  • February 4, 2010

COMPLETION DATE

  • October 15, 2010

PROJECT AMOUNT

  • $4,875,873.50

PROGRESS

  • APBN Inc., is finishing applying the polyurethane finish coat tothe north tower along the north side of the lift span up to the south side of the bridge tender’s office.
  • Color of the finish coat is Federal color number 595B-14151 (green gloss)
  • The containment on the north side of the structure has been taken down and will be placed on the south side of the bridge.
  • Contractor will commence the abrasive blasting on the south side of the structure before the end of August.
  • W. 3rd Street remains closed to traffic at the bridge, detour route is posted.

 

 

CONSTRUCTION PROJECT UPDATE

W. 3rd STREET BRIDGE No. 1:045

OVER THE CUYAHOGA RIVER

CITY OF CLEVELAND

DATE:

  • July 19, 2010

NOTICE TO PROCEED

  • February 4, 2010

COMPLETION DATE

  • October 15, 2010

PROJECT AMOUNT

  • $4,875,873.50

PROGRESS

  • APBN Inc., continues stripe coating epoxy paint on the northtower and also on the lower level of the north side of the lift span.
  • Once sufficient areas have been strip coated, contractor is following up with the spraying of epoxy paint.
  • Beams and cross bracing below the bridge deck on the lift span has been painted with epoxy paint.
  • The two main sheaves on the north tower along with all steel above the top concrete pad has been coated with the epoxy paint.
  • Painting continues on the beams, cross bracing and stairs, working toward ground elevation.
  • Contractor will caulk joints between adjacent steel members once epoxy painting is completed on the enclosed portion of the lift span and the north tower.
    • The bridge will be coated with an urethane finish coat Federal color number 595B-14151 (green gloss).

 

 

 

 

                    CONSTRUCTION PROJECT UPDATE


WEST BRIDGE STREET BRIDGE No. 256 OVER THE EAST BRANCH OF ROCKY RIVER CITY OF BEREA

DATE:

 June 17, 2010

NOTICE TO PROCEED

 June 7, 2010

COMPLETION DATE

 November 2010

PROJECT AMOUNT

 $1,086,086.00

PROGRESS

 West Bridge Street Bridge No. 256 has been closed to facilitate the
demolition and removal of the existing structure.
 The closing will remain in effect throughout the demolition of the
existing structure repair and replacement of the bridge abutments and
the complete replacement of the bridge deck, sidewalks and bridge railing.
 A detour route has been established.


 

CONSTRUCTION PROJECT UPDATE

W. 3rd STREET BRIDGE No. 1:045

OVER THE CUYAHOGA RIVER

CITY OF CLEVELAND

DATE:

  • May 21, 2010

NOTICE TO PROCEED

  • February 4, 2010

COMPLETION DATE

  • October 15, 2010

PROJECT AMOUNT

  • $4,875,873.50

PROGRESS

  • APBN Inc. continues to hang tarpaulin cables on the northern

tower, all four sides, scaffolding to support tarpaulin above the

pulley housings on the north tower have been erected.

  • Contractor continues to wrap pulley cables, electrical cables,

electric boxes and other items that are not to be painted.

  • Bridge Tenders room on lift span has been wrapped.

 

 

CONSTRUCTION PROJECT UPDATE

W. 3rd STREET BRIDGE No. 1:045

OVER THE CUYAGOGA RIVER

CITY OF CLEVELAND

DATE:

  • May 5, 2010

NOTICE TO PROCEED

  • February 4, 2010

COMPLETION DATE

  • October 15, 2010

PROJECT AMOUNT

  • $4,875,873.50

PROGRESS

  • On April 20, 2010 APBN Inc. has closed the bridge to vehicular and

pedestrian traffic, detour has been posted.

  • Contractor installing rigging for containment on the north tower

along with 60% of the lift span.

  • Bridge was raised on Friday April 30th for a duration not to exceed

160 calendar days.

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Monday, August 16, 2010.

© 1999-2010 Cuyahoga County Engineer's Office