CONSTRUCTION PROJECT UPDATE
W. 3rd STREET BRIDGE No. 1:045
OVER THE CUYAHOGA RIVER
CITY OF CLEVELAND
DATE:
NOTICE TO PROCEED
COMPLETION DATE
PROJECT AMOUNT
$4,875,873.50
PROGRESS
- APBN Inc., is finishing applying the polyurethane finish coat tothe
north tower along the north side of the lift span up to the south side
of the bridge tender’s office.
- Color of the finish coat is Federal color number 595B-14151 (green
gloss)
- The containment on the north side of the structure has been taken
down and will be placed on the south side of the bridge.
- Contractor will commence the abrasive blasting on the south side of
the structure before the end of August.
- W. 3rd Street remains closed to traffic at the bridge,
detour route is posted.
CONSTRUCTION PROJECT UPDATE
W. 3rd STREET BRIDGE No. 1:045
OVER THE CUYAHOGA RIVER
CITY OF CLEVELAND
DATE:
NOTICE TO PROCEED
COMPLETION DATE
PROJECT AMOUNT
$4,875,873.50
PROGRESS
- APBN Inc., continues stripe coating epoxy paint on the northtower
and also on the lower level of the north side of the lift span.
- Once sufficient areas have been strip coated, contractor is
following up with the spraying of epoxy paint.
- Beams and cross bracing below the bridge deck on the lift span has
been painted with epoxy paint.
- The two main sheaves on the north tower along with all steel above
the top concrete pad has been coated with the epoxy paint.
- Painting continues on the beams, cross bracing and stairs, working
toward ground elevation.
- Contractor will caulk joints between adjacent steel members once
epoxy painting is completed on the enclosed portion of the lift span and
the north tower.
- The bridge will be coated with an urethane finish coat Federal
color number 595B-14151 (green gloss).
CONSTRUCTION PROJECT UPDATE
WEST BRIDGE STREET BRIDGE No. 256 OVER THE EAST BRANCH OF ROCKY RIVER CITY
OF BEREA
DATE:
June 17, 2010
NOTICE TO PROCEED
June 7, 2010
COMPLETION DATE
November 2010
PROJECT AMOUNT
$1,086,086.00
PROGRESS
West Bridge Street Bridge No. 256 has been closed to facilitate the
demolition and removal of the existing structure.
The closing will remain in effect throughout the demolition of the
existing structure repair and replacement of the bridge abutments and
the complete replacement of the bridge deck, sidewalks and bridge railing.
A detour route has been established.
CONSTRUCTION PROJECT UPDATE
W. 3rd STREET BRIDGE No. 1:045
OVER THE CUYAHOGA RIVER
CITY OF CLEVELAND
DATE:
NOTICE TO PROCEED
COMPLETION DATE
PROJECT AMOUNT
$4,875,873.50
PROGRESS
- APBN Inc. continues to hang tarpaulin cables on the northern
tower, all four sides, scaffolding to support tarpaulin above the
pulley housings on the north tower have been erected.
- Contractor continues to wrap pulley cables, electrical cables,
electric boxes and other items that are not to be painted.
- Bridge Tenders room on lift span has been wrapped.
CONSTRUCTION PROJECT UPDATE
W. 3rd STREET BRIDGE No. 1:045
OVER THE CUYAGOGA RIVER
CITY OF CLEVELAND
DATE:
NOTICE TO PROCEED
February 4, 2010
COMPLETION DATE
October 15, 2010
PROJECT AMOUNT
$4,875,873.50
PROGRESS
On April 20, 2010 APBN Inc. has closed the bridge to vehicular and
pedestrian traffic, detour has been posted.
- Contractor installing rigging for containment on the north tower
along with 60% of the lift span.
- Bridge was raised on Friday April 30th for a duration not
to exceed
160 calendar days.
This page has been accessed times
since February 26, 2004
and was last updated on
Monday, August 16, 2010.