WEEKLY PROJECT UPDATE
WARRENSVILLE CENTER ROAD BRIDGE NO. 205 REPLACEMENT
OVER NORFOLK-SOUTHERN RAILROAD
WARRENSVILLE HEIGHTS
DATE
Thursday, November 8, 2007
NOTICE TO PROCEED
July 1, 2007
COMPLETION DATE
November 2008
PROJECT AMOUNT
$2,407,209.20
PROGRESS
The traffic pattern will change on Tuesday, November 13, 2007.
- Two-way traffic will be maintained by use of a temporary traffic
signal.
- Will be like this for the next 4-6 weeks.
- Necessary in order to complete work on the bridge.
WARRENSVILLE CENTER ROAD BRIDGE NO. 205 REPLACEMENT
OVER NORFOLK-SOUTHERN RAILROAD
WARRENSVILLE HEIGHTS
DATE
Wednesday, December 5, 2007
NOTICE TO PROCEED
July 1, 2007
COMPLETION DATE
November 2008
PROJECT AMOUNT
$2,407,209.20
PROGRESS
As of Wednesday, December 5, 2007, the temporary signalization,
detours and new traffic pattern were removed. The roadway is reopened to
two-way traffic.
WEEKLY PROJECT UPDATE
WARRENSVILLE CENTER ROAD BRIDGE NO. 205 REPLACEMENT
OVER NORFOLK-SOUTHERN RAILROAD
WARRENSVILLE HEIGHTS
DATE
Tuesday, August 19, 2008
NOTICE TO PROCEED
July 1, 2007
COMPLETION DATE
November 2008
PROJECT AMOUNT
$2,407,209.20
PROGRESS
At 1:00 p.m. on Tuesday, August 19. 2008, and emergency closure of
the bridge will take place. This closure will last for a minimum of 4
weeks. During this time, ALL traffic must use an alternate route.
This page has been accessed times
since February 26, 2004
and was last updated on
Tuesday, August 19, 2008.