Construction Projects Update

 


CONSTRUCTION PROJECT UPDATE

CANNON ROAD BRIDGE NO. 140 REPLACEMENT

OVER A BRANCH OF TINKERS CREEK

SOLON

 

DATE

November 4, 2009

NOTICE TO PROCEED

June 8, 2009

START DATE

June 8, 2009

COMPLETION DATE

October 16, 2009

PROJECT AMOUNT

$527,443.55

PROGRESS

  • All construction has been completed. The bridge is open to all traffic.
  • Work expected in the upcoming weeks:
  • Completion of punch list items.

 

 

CONSTRUCTION PROJECT UPDATE

CANNON ROAD BRIDGE NO. 140 REPLACEMENT

OVER A BRANCH OF TINKERS CREEK

SOLON

 

DATE

August 27, 2009

NOTICE TO PROCEED

June 8, 2009

START DATE

June 8, 2009

COMPLETION DATE

October 16, 2009

PROJECT AMOUNT

$527,443.55

PROGRESS

  • On Thursday, August 27, 2009, the bridge will be open to ALL traffic. The bridge has been closed to traffic since June 2009.
  • Overall project will not be completed until October 2009.

 

CONSTRUCTION PROJECT UPDATE

CANNON ROAD BRIDGE NO. 140 REPLACEMENT

OVER A BRANCH OF TINKERS CREEK

SOLON

 

DATE

June 2, 2009

NOTICE TO PROCEED

June 8, 2009

START DATE

June 8, 2009

COMPLETION DATE

October 16, 2009

PROJECT AMOUNT

$527,443.55

PROGRESS

  • Construction will commence on the replacement of Cannon Road Bridge No. 140 on Monday, June 8, 2009.
  • The bridge will be closed to all traffic throughout the course of construction. The following roads will be used for the detour route: Harper Road, Aurora Road and Richmond Road.

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Thursday, November 05, 2009.

© 1999-2004 Cuyahoga County Engineer's Office