Construction Projects Update

 


CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Thursday, September 21, 2006

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Contractor to place two message boards (one at Brainard/Cedar and one at Lander/Cedar) that say, "Cedar Road construction begins October 2. Expect delays."
  • The first phase of work will include installing the temporary pavement on the north side of Cedar for westbound traffic.
  • Public is advised to use caution in the project site while this is being done.

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Friday, October 20, 2006

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Hydrant relocation began Wednesday, October 18, 2006, and will continue.
  • Excavation for the temporary road will begin on Monday, October 23, 2006.
  • Expected work in the next three weeks:
    • Waterline relocation and installing pavement for temporary road.

 

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Monday, November 6, 2006

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Work on temporary road continues and is to be finished around Thanksgiving.
  • Hydrant work is 90% complete, and additional water work will continue.
  • Signaling at Cedar/Landerbrook has changed.
  • Delays are to be expected throughout the duration of the project. Alternate routes are strongly recommended.

For more updated info on this project please click on link below.

http://www.geocities.com/cedarroadproject/

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Monday, November 27, 2006

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Traffic to be switched on November 29, 2006, to the temporary pavement.
  • Westbound traffic will use the temporary pavement, Eastbound traffic will use the existing westbound lane.
  • The Cedar/Brainard intersection is not affected. The work zone starts 400 ft. east of this intersection.
  • Work expected to start next week on underground utilities.

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Monday, January 22, 2007

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Underground utility work continues on the south side of Cedar Road. This includes installation of a new sanitary sewer and a 24" waterline relocation.
  • Work has begun on Cedar Road Culvert No. 11. This includes the demolition of this culvert. The pre-cast sections for the drive culvert and roadway culvert will be set this week.
  • Expected work:
    • The continuation of the sanitary sewer installation and finishing the drive culvert and the south half of the Cedar Road culvert.
    • Storm sewer work is expected to start on the first of second week of February.

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Thursday, May 31, 2007

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Lander Road concrete installation is complete. The asphalt overlay is the next item to be completed.
  • Underground utility work is 99% complete.
  • Excavation of the south side of roadway is near completion.
  • Stone will be placed from the culvert to Brainard Road. Please use caution because trucks will be pulling in and out of the work zone.
  • The light at Cedar Road and Lander Road has been changed. It is now almost identical to what it was before the project started. This was done at the request of the City of Mayfield Heights.

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Friday, June 29, 2007

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • The south side of Cedar Road has been paved with three courses of asphalt to date with the surface course left (the surface will be completed last after the north side has been completed in similar manner).
  • The widening of Brainard/Cedar will be completed on the east side in 30 days.
  • The Cedar/Windy Hill intersection remains closed.

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Monday, October 22, 2007

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • The final asphalt surface course is scheduled for installation on October 24, 2007 and October 25, 2007, weather pending.
  • Police officers will be on hand to assist traffic.
  • Driveway installation and grading will continue this Fall. Temporary traffic zones will be set in place for this.
  • Final landscaping will be completed in the Spring.

 

CONSTRUCTION PROJECT UPDATE

CEDAR ROAD REHABILITATION

BRAINARD ROAD TO LANDER ROAD

LYNDHURST, MAYFIELD HEIGHTS & PEPPER PIKE

DATE:

  • Monday, November 5, 2007

NOTICE TO PROCEED

  • October 2, 2006

COMPLETION DATE

  • June 2, 2008

PROJECT AMOUNT

  • $5,160,899.00

PROGRESS

  • Cedar Road was open to traffic on Thursday, November 1, 2007.
  • Final striping was completed on Friday, November 2, 2007.
  • Temporary work zones will be utilized to install drive aprons, complete linear grading, to finish traffic signalization and signage.
  • Final landscaping will be done in the spring.

 

 

 

 

 