September 30, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Completion of punch list items.
  • Work to take place in the month of October: completion of traffic signalization and completion of punch list items.

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

September 1, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • The existing aprons and sidewalks have been removed on the east side of Stearns Road.
  • The placement of topsoil and grass seed on the east side of Stearns Road has been completed.
  • -The placement of concrete pavement, curbs, driveway aprons and sidewalks are complete.
  • The placement of traffic signalization continues.
  • Guard rail placement and signage are complete. All permanent pavement markings have been placed.
  • Stearns Road was reopened to two-way traffic on August 24, 2009, a year earlier than the contract completion date.
  • Work to take place the month of September: completion of traffic signalization and completion of punch list items.

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

August 10, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Traffic remains one-way southbound on the west side of Stearns Road from I-480 to 1,000 feet south of Cook Road.
  • Existing pavement, aprons and sidewalks on the east side of Stearns Road and the east end of Cook Road.
  • Underdrain has been placed, castings have been adjusted and concrete has been placed for new pavement and curb at the Cook/Stearns intersection and on Stearns Road from Cook Road to the north end of the project.
  • Traffic signalization is being placed at the Cook/Stearns intersection.
  • Cook Road was opened to through traffic on July 9th.
  • Work for August includes: completing the placement of new concrete drive aprons, sidewalks and landscaping on the right side of Stearns Road, completion of signalization and reopening Stearns Road to two-way traffic.

 

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

July 7, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Traffic remains one-way southbound on new pavement on the west side of Stearns Road from I-480 to 1,000 feet south of Cook Road.
  • Landscaping operations have been completed.
  • The placement of concrete for new pavement, curb, walk and drive aprons has been completed on the west side of the road.
  • The existing pavement, aprons and sidewalk are currently being removed on the east side of Stearns Road north of Dorchester Road and the east end of Cook Road.
  • Concrete is being placed for new pavement and curb at the Cook/Stearns intersection and Stearns Road south of the intersection.
  • Work expected for the month of July includes: pavement removal, cement stabilization and placement of pavement curb and aprons and sidewalks on the east side of Stearns Road.

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

Tuesday, July 9, 2008

NOTICE TO PROCEED

August 18, 2008

START DATE

August 18, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

Monday, September 8, 2008

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Monday, September 15, 2008, Stearns Road will be closed to all thru traffic between Cook Road and Bagley Road.
  • This closure will last for 28 days.
  • This closure is necessary in order to replace Stearns Road Culvert No. 5, which is part of the aforementioned project.
  • Detours will be posted.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

Monday, October 6, 2008

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Contractor continues to build Stearns Road Culvert No. 5.
  • Stearns Road remains closed but is scheduled to be reopened by Monday, October 13, 2008.
  • This week, concrete for the east side wing walls will be placed. In addition, porous backfill and embankment material will be placed.
  • A new roadway will be placed and opened.
  • After culvert work is complete, underground utility work will begin.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

Monday, November 17, 2008

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Monday, November 24, 2008, Stearns Road will be closed to all northbound traffic from south of Dorchester to north of Cook Road until further notice.
  • One-way traffic southbound will be maintained, as will residential access.
  • This closure is necessary in order to install sanitary sewers, water main and storm sewers this winter.
  • A detour route has been established: west on Cook Road, north on Barton, east on Lorain Road to Stearns Road.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

Monday, December 8, 2008

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Placement of 15" sanitary conduit, manholes and 6" lateral connections continue to be placed.
  • Sanitary Sewer trenches have been excavated and concrete has been placed in trenches.
  • Water quality control structures and water service connections have been placed.
  • Stearns Road is southbound only between I-480 and Cook Road. A detour route has been established for northbound motorists.
  • Upcoming work: placement of sanitary sewer and 6" lateral connections, placement of concrete in trenches and commencement of water work.

DATE

Tuesday, January 13, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Placement of 15" sanitary conduit and manholes. Placement of 6" lateral connections to residences on Cook Road and on Stearns Road.
  • Sanitary sewers have been excavated. Concrete has been placed in the trenches for the safety of the motoring public.
  • Placement of 18" Type C conduit began, as well as placement of manholes and lateral connections for drainage on Stearns Road.
  • Upcoming work includes additional drainage work, placement of water line and the completion of sanitary work.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

February 4, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • The placements of 6" sanitary lateral connections to residences on Cook Road and Stearns Road have been completed.
  • Pressure testing of the sanitary line and manholes have been performed and completed.
  • The placement of 15", 18", 21", 24" 30" & 36" Type C conduits, manholes and 6" lateral connections for storm drainage on Stearns Road and Cook Road have been completed.
  • The placement of Type 2 water quality control structures has been completed.
  • New 12" ductile iron water main and hydrants have been placed.
  • Sanitary and storm line trenches have been excavated and concrete has been placed in these trenches for the safety of the motoring public.
  • Work projected for the next month: completion of drainage work & completion of water work.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

March 26, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Wednesday, April 2, 2009, a new work zone will be established between just south of I-480 to Dorchester on Stearns Road. Southbound traffic will be maintained and northbound traffic will be detoured. This new pattern will last for 1-2 months, weather permitting.

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

April 3, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Conduit, manholes, catch basins, side ditch inlets and lateral connections for storm drainage have been placed.
  • The perimeter silt fence has been placed in various locations.
  • Hydrants have been placed, the new 12" ductile iron water main has been tapped and the water service connections have been completed.
  • New traffic pattern is now in effect: southbound traffic only from the 1-480 overpass to Cook Road. Two-way traffic permitted north of the overpass.
  • Work to take place in April includes pavement removal, subgrade stabilization and placement of concrete for new roadway.

 

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

April 14, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Monday, April 20, 2009, the western half of Stearns Road, from I-480 to 1,000 feet south of Cook Road, will be closed.
  • A detour route will be established for northbound motorists.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

May 4, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • Traffic on Stearns Road is one-way southbound from I-480 to 1,000 feet south of Cook Road.
  • Existing pavement has been removed on Stearns Road. Concrete will be placed for the pavement and curb.
  • Work for May includes additional pavement removal, cement stabilization and concrete placement.

CONSTRUCTION PROJECT UPDATE

CROCKER ROAD-STEARNS ROAD EXTENSION

CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS FROM LORAIN TO I-480

CITIES OF NORTH OLMSTED & WESTLAKE

DATE:

May 4, 2009

NOTICE TO PROCEED

March 15, 2007

COMPLETION DATE

September 1, 2009

PROJECT AMOUNT

$13,299,797.20

PROGRESS

  • The 10" reinforced concrete pavement on the northwest and northeast sides of the Crocker Road/Center Ridge Road intersection is being placed.
  • Will begin grading for placement of proposed 4.5" concrete walk at the Crocker Road/Center Ridge Road intersection.
  • Touch up work is being completed on the noise barrier wall.
  • Placement of survey monuments.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

May 15, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Tuesday, May 19, 2009 and Wednesday, May 20, 2009, concrete will be poured for the new roadway on Stearns Road just south of I-480, weather permitting.
  • Significant delays are to be expected.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

May 18, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • The concrete pouring will be delayed. Initially it was to begin on Tuesday, May 19, 2009 and Wednesday, May 20, 2009.
  • The new dates for the pouring are Wednesday, May 20, 2009 and Thursday, May 21, 2009, weather permitting.
  • Significant delays are to be expected.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

May 22, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • On Thursday, May 28, 2009, the eastern part of Stearns Road will be closed from I-480 to 1,000 feet south of Cook Road. At this time, the eastern half of the Cook Road-Stearns Road intersection will be closed as well.
  • Traffic will be southbound only. A detour route has been established for northbound motorists. Detour signs will be posted.
  • This closure will last for approximately 3-4 weeks, weather permitting.

WEEKLY PROJECT UPDATE

COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT

0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480, INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5

OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED

 

DATE

May 26, 2009

NOTICE TO PROCEED

August 18, 2008

START DATE

August 15, 2008

COMPLETION DATE

August 18, 2010

PROJECT AMOUNT

$5,996,078.98

PROGRESS

  • The change of the traffic pattern has been delayed. Initially, it was to change on Thursday, May 28, 2009. However, due to impending weather, this will now occur on Monday, June 1, 2009 and will last for 3-4 weeks.
  • At this time, the eastern half of Stearns Road from I-480 to 1,000 feet south of Cook Road will be closed. Southbound traffic will be maintained on the western half of the roadway. In addition, the eastern half of the Cook-Stearns intersection will be closed.

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Wednesday, October 07, 2009.

© 1999-2009 Cuyahoga County Engineer's Office