DATE
September 30, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
- Completion of punch list items.
- Work to take place in the month of October: completion of traffic
signalization and completion of punch list items.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
September 1, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
- The existing aprons and sidewalks have been removed on the east side
of Stearns Road.
- The placement of topsoil and grass seed on the east side of Stearns
Road has been completed.
- -The placement of concrete pavement, curbs, driveway aprons and
sidewalks are complete.
- The placement of traffic signalization continues.
- Guard rail placement and signage are complete. All permanent
pavement markings have been placed.
- Stearns Road was reopened to two-way traffic on August 24, 2009, a
year earlier than the contract completion date.
- Work to take place the month of September: completion of traffic
signalization and completion of punch list items.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
August 10, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
- Traffic remains one-way southbound on the west side of Stearns Road
from I-480 to 1,000 feet south of Cook Road.
- Existing pavement, aprons and sidewalks on the east side of Stearns
Road and the east end of Cook Road.
- Underdrain has been placed, castings have been adjusted and concrete
has been placed for new pavement and curb at the Cook/Stearns
intersection and on Stearns Road from Cook Road to the north end of the
project.
- Traffic signalization is being placed at the Cook/Stearns
intersection.
- Cook Road was opened to through traffic on July 9th.
- Work for August includes: completing the placement of new concrete
drive aprons, sidewalks and landscaping on the right side of Stearns
Road, completion of signalization and reopening Stearns Road to two-way
traffic.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
July 7, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
- Traffic remains one-way southbound on new pavement on the west side
of Stearns Road from I-480 to 1,000 feet south of Cook Road.
- Landscaping operations have been completed.
- The placement of concrete for new pavement, curb, walk and drive
aprons has been completed on the west side of the road.
- The existing pavement, aprons and sidewalk are currently being
removed on the east side of Stearns Road north of Dorchester Road and
the east end of Cook Road.
- Concrete is being placed for new pavement and curb at the
Cook/Stearns intersection and Stearns Road south of the intersection.
- Work expected for the month of July includes: pavement removal,
cement stabilization and placement of pavement curb and aprons and
sidewalks on the east side of Stearns Road.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
Tuesday, July 9, 2008
NOTICE TO PROCEED
August 18, 2008
START DATE
August 18, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
Monday, September 8, 2008
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Monday, September 15, 2008, Stearns Road will be closed to all
thru traffic between Cook Road and Bagley Road.
This closure will last for 28 days.
This closure is necessary in order to replace Stearns Road Culvert
No. 5, which is part of the aforementioned project.
Detours will be posted.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
Monday, October 6, 2008
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
Contractor continues to build Stearns Road Culvert No. 5.
Stearns Road remains closed but is scheduled to be reopened by
Monday, October 13, 2008.
This week, concrete for the east side wing walls will be placed. In
addition, porous backfill and embankment material will be placed.
A new roadway will be placed and opened.
After culvert work is complete, underground utility work will begin.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
Monday, November 17, 2008
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Monday, November 24, 2008, Stearns Road will be closed to all
northbound traffic from south of Dorchester to north of Cook Road until
further notice.
One-way traffic southbound will be maintained, as will residential
access.
This closure is necessary in order to install sanitary sewers, water
main and storm sewers this winter.
A detour route has been established: west on Cook Road, north on
Barton, east on Lorain Road to Stearns Road.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
Monday, December 8, 2008
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
Placement of 15" sanitary conduit, manholes and 6" lateral
connections continue to be placed.
Sanitary Sewer trenches have been excavated and concrete has been
placed in trenches.
Water quality control structures and water service connections have
been placed.
Stearns Road is southbound only between I-480 and Cook Road. A
detour route has been established for northbound motorists.
Upcoming work: placement of sanitary sewer and 6" lateral
connections, placement of concrete in trenches and commencement of water
work.
DATE
Tuesday, January 13, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
Placement of 15" sanitary conduit and manholes. Placement of 6"
lateral connections to residences on Cook Road and on Stearns Road.
Sanitary sewers have been excavated. Concrete has been placed in the
trenches for the safety of the motoring public.
Placement of 18" Type C conduit began, as well as placement of
manholes and lateral connections for drainage on Stearns Road.
Upcoming work includes additional drainage work, placement of water
line and the completion of sanitary work.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
February 4, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
The placements of 6" sanitary lateral connections to residences on
Cook Road and Stearns Road have been completed.
Pressure testing of the sanitary line and manholes have been
performed and completed.
The placement of 15", 18", 21", 24" 30" & 36" Type C conduits,
manholes and 6" lateral connections for storm drainage on Stearns Road
and Cook Road have been completed.
The placement of Type 2 water quality control structures has been
completed.
New 12" ductile iron water main and hydrants have been placed.
Sanitary and storm line trenches have been excavated and concrete
has been placed in these trenches for the safety of the motoring public.
Work projected for the next month: completion of drainage work &
completion of water work.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
March 26, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Wednesday, April 2, 2009, a new work zone will be established
between just south of I-480 to Dorchester on Stearns Road. Southbound
traffic will be maintained and northbound traffic will be detoured. This
new pattern will last for 1-2 months, weather permitting.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
April 3, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
Conduit, manholes, catch basins, side ditch inlets and lateral
connections for storm drainage have been placed.
The perimeter silt fence has been placed in various locations.
Hydrants have been placed, the new 12" ductile iron water main has
been tapped and the water service connections have been completed.
New traffic pattern is now in effect: southbound traffic only from
the 1-480 overpass to Cook Road. Two-way traffic permitted north of the
overpass.
Work to take place in April includes pavement removal, subgrade
stabilization and placement of concrete for new roadway.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
April 14, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Monday, April 20, 2009, the western half of Stearns Road, from
I-480 to 1,000 feet south of Cook Road, will be closed.
A detour route will be established for northbound motorists.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
May 4, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
Traffic on Stearns Road is one-way southbound from I-480 to 1,000
feet south of Cook Road.
Existing pavement has been removed on Stearns Road. Concrete will be
placed for the pavement and curb.
Work for May includes additional pavement removal, cement
stabilization and concrete placement.
CONSTRUCTION PROJECT UPDATE
CROCKER ROAD-STEARNS ROAD EXTENSION
CENTER RIDGE ROAD TO LORAIN ROAD; WIDENING OF STEARNS
FROM LORAIN TO I-480
CITIES OF NORTH OLMSTED & WESTLAKE
DATE:
May 4, 2009
NOTICE TO PROCEED
March 15, 2007
COMPLETION DATE
September 1, 2009
PROJECT AMOUNT
$13,299,797.20
PROGRESS
The 10" reinforced concrete pavement on the northwest and northeast
sides of the Crocker Road/Center Ridge Road intersection is being
placed.
Will begin grading for placement of proposed 4.5" concrete walk at
the Crocker Road/Center Ridge Road intersection.
Touch up work is being completed on the noise barrier wall.
Placement of survey monuments.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
May 15, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Tuesday, May 19, 2009 and Wednesday, May 20, 2009, concrete will
be poured for the new roadway on Stearns Road just south of I-480,
weather permitting.
Significant delays are to be expected.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
May 18, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
The concrete pouring will be delayed. Initially it was to begin on
Tuesday, May 19, 2009 and Wednesday, May 20, 2009.
The new dates for the pouring are Wednesday, May 20, 2009 and
Thursday, May 21, 2009, weather permitting.
Significant delays are to be expected.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
May 22, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
On Thursday, May 28, 2009, the eastern part of Stearns Road will be
closed from I-480 to 1,000 feet south of Cook Road. At this time, the
eastern half of the Cook Road-Stearns Road intersection will be closed
as well.
Traffic will be southbound only. A detour route has been established
for northbound motorists. Detour signs will be posted.
This closure will last for approximately 3-4 weeks, weather
permitting.
WEEKLY PROJECT UPDATE
COOK ROAD-STEARNS ROAD INTERSECTION IMPROVEMENT
0.2 MILES SOUTH OF COOK ROAD TO THE NORTH SIDE OF 1-480,
INCLUDING THE REPLACEMENT OF STEARNS ROAD CULVERT NO. 5
OLMSTED TOWNSHIP AND THE CITY OF NORTH OLMSTED
DATE
May 26, 2009
NOTICE TO PROCEED
August 18, 2008
START DATE
August 15, 2008
COMPLETION DATE
August 18, 2010
PROJECT AMOUNT
$5,996,078.98
PROGRESS
The change of the traffic pattern has been delayed. Initially, it
was to change on Thursday, May 28, 2009. However, due to impending
weather, this will now occur on Monday, June 1, 2009 and will last for
3-4 weeks.
At this time, the eastern half of Stearns Road from I-480 to 1,000
feet south of Cook Road will be closed. Southbound traffic will be
maintained on the western half of the roadway. In addition, the eastern
half of the Cook-Stearns intersection will be closed.