EDDY ROAD REPAIR & RESURFACING
PRE-CON
Description: Repair &
resurfacing of Eddy Road from Euclid Avenue to the East Cleveland North
Corporation Line in the City of East Cleveland.
Contractor: Vandra Brothers Construction, Inc.
Area Engineer: Joe Charif
Cell: (216) 701-1262
Project Engineer: Rich Orosz
Cell:
Project Cost: $809,232.80
Notice to Proceed: April 14, 2008
Start Date: April 14, 2008
Completion Date: August 30, 2008
Funding: Ohio Public Works Commission and Cuyahoga
County
Notes:
- Project Supervisor for Vandra Brothers is Bruno Melaragno
- Traffic maintained throughout course of project.
PROJECT UPDATE
EDDY ROAD REPAIR & RESURFACING
EUCLID AVENUE TO THE EAST CLEVELAND NORTH CORPORATION
LINE
EAST CLEVELAND
DATE
NOTICE TO PROCEED
April 15, 2008
COMPLETION DATE
August 15, 2008
PROJECT AMOUNT
$809,232.80
CONTRACTOR
Vandra Brothers Construction, Inc.
FUNDING
Ohio Public Works Commission and Cuyahoga County
PROGRESS
On Tuesday, April 15, 2008, the subcontractor began milling the
existing asphalt overlay, worked on full/partial depth repairs to the
existing brick/concrete base materials, and then placed an asphalt
overlay using and intermediate course of material with type 2A fiber.
Currently, the contractor is removing existing curb, sidewalk and
driveway aprons on the southeast side of the project toward Euclid
Avenue.
Upon the removal, crew will grade, form, install, base materials and
place new concrete curb, walks and aprons.
One-way traffic southbound is being enforced from Euclid Avenue to
E. 128th Street. Detour is Euclid Avenue to superior Ave. to
E. 123rd Street to Arlington back to Eddy Road.
PROJECT UPDATE
EDDY ROAD REPAIR & RESURFACING
EUCLID AVENUE TO THE EAST CLEVELAND NORTH CORPORATION
LINE
EAST CLEVELAND
DATE
NOTICE TO PROCEED
April 15, 2008
COMPLETION DATE
August 15, 2008
PROJECT AMOUNT
$809,232.80
CONTRACTOR
Vandra Brothers Construction, Inc.
FUNDING
Ohio Public Works Commission and Cuyahoga County
PROGRESS
Construction of the new concrete curb, walks and aprons along the
east side of the project has been completed. The adjustment of roadway
castings has also been completed.
Existing curb, sidewalk and driveway aprons are currently being
removed on the southwest side of the project and working toward the
Cleveland Corp. Line.
Following the removal process, crews are grading, forming,
installing base materials and placing new concrete curb, walks and
aprons.
One-way traffic southbound from Euclid to E. 128th
Street. A detour has been posted for northbound traffic: Euclid Avenue,
west on Superior Avenue, north on E. 123rd Street, east on
Arlington to Eddy Road.
© 1999-2008 Cuyahoga County Engineer's Office |