CONSTRUCTION PROJECT UPDATE
MILES RD/HARPER RD INTERSECTION IMPROVEMENT
IN THE CITY OF SOLON & ORANGE VILLAGE
DATE:
NOTICE TO PROCEED
START DATE
COMPLETION DATE
PROJECT AMOUNT
$780,452.14
PROGRESS
- PHASE A & B: Construction is now completed (pavement widening and
installation of curb on the north and south sides of Miles Road,
including placement of the intermediate course asphalt).
- PHASE C: Construction is now in progress. This work will include
adjusting of roadway castings, saw-cutting and installation of traffic
oop detectors at Harper Road, Miles Road and the Farmers Market
intersections and placement of pavement fabric followed by final Surface
course paving and pavement striping.
Work expected in the upcoming weeks includes:
- Additional signalization work will continue during the next few
months: trenching/boring of conduits, mounting of controller boxes and
signal supports/mast arms and installation of pull boxes.
- Erection of manufactured block retaining wall system at the Mt. Hope
Cemetery.
- Placement of new commercial/residential asphalt and concrete
driveway aprons on the south side of roadway.
- Installing ADA compliant sidewalks /ramps at the Miles Rd. Harper
Rd. intersection as well as the Miles Farmers Market driveway.
- During this project two-way traffic will be maintained but long
delays are to be expected during working hours.
Email:
milesatharper@yahoo.com
Field Office Phone: 440-248-4404
Field Office Fax: 440-248-4788
CONSTRUCTION PROJECT UPDATE
MILES RD/HARPER RD INTERSECTION IMPROVEMENT
IN THE CITY OF SOLON & ORANGE VILLAGE
DATE:
NOTICE TO PROCEED
July 6, 2010
START DATE
July 12, 2010
COMPLETION DATE
May 2011
PROJECT AMOUNT
$780,452.14
PROGRESS
PHASE A: Construction on the north side of Miles Road and
Harper Road intersection continues.
- Contractor completing roadway excavation and embankment and the
placement of 9" of #301 asphalt base material. Construction of new
residential driveway aprons using asphalt and concrete materials.
- Work scheduled to be shifted to the south side of roadway where
Phase B construction will begin. This work will include excavation of
existing pavement and base materials, installation of new 12" RCP storm
sewer system and 7’ pavement widening.
- C.A. Agresta Construction Company has completed the auguring for and
placement of concrete anchor foundations for new signal supports at the
Miles Farmers Market driveway.
- Additional signalization work will continue during the month;
trenching/boring of conduits, mounting of signal supports/mast arms and
installation of pull boxes
Email:
milesatharper@yahoo.com
Field Office Phone: 440-248-4404
Field Office Fax: 440-248-4788
This page has been accessed times
since February 26, 2004
and was last updated on
Wednesday, September 01, 2010.
© 1999-2010 Cuyahoga County Engineer's Office |