|
![[ Cuyahoga County Engineer's Seal ]](../images/small_white_logo.gif)

 |
|
The Cuyahoga County Engineer's Office
Construction Projects Update
CONSTRUCTION PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
September 9, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
- All contractual work has been completed.
- Roadway is open to traffic the entire length of the project.
- Temporary lane closures may occur as punch list work is being
performed.
- Work expected in the upcoming weeks:
- Punch list items
- Final inspection
CONSTRUCTION PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
August 10, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 2—(800’ west of) State Road to Broadview Road
- On Thursday, July 30, 2009, and on Monday, August 3, 2009, the
surface course of asphalt was placed on this stretch of roadway. All
lanes of traffic were restored as of August 4, 2009. Temporary striping
has been placed for maintenance of traffic.
Work to be expected during the upcoming weeks includes:
- Backfilling/landscaping at areas along the back of new curbs.
- Continue placement of new type G reflective signage (in Sections 1
& 2).
- Removal of temporary striping and install permanent #645 polyester
pain markings.
- General clean-up.
Final inspection/punch list items
CONSTRUCTION PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
June 30, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 2—(800’ west of) State Road to Broadview Road
- Rehabilitation work is currently on the south side of Snow Road with
two-way traffic (one lane in each direction) maintained on the newly
placed asphalt intermediate course on the north side of the road. Delays
are to be expected during construction hours.
Work to be expected during the upcoming weeks includes:
- Completion of full-depth repairs to the existing concrete base.
- Begin to identify/mark areas designated for partial asphalt depth
repairs.
- Placement of intermediate asphalt on top of repaired concrete base
surfaces.
- Backfilling/landscaping at areas along the back of new curbs.
- Remove, inspect and rebuild/adjust to grade various manhole, catch
basin and water valve castings. New iron casting will be used in areas
as designated.
- Remove and reconstruct existing sidewalk curb ramps to ADA
compliance.
Placement of new type G reflective signage (Sections
CONSTRUCTION PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
June 3, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 2—(800’ west of) State Road to Broadview Road
- Work has now shifted to the south side of Snow Road. Two-way traffic
(one lane in each direction) will be maintained on the newly placed
asphalt intermediate surface course along the north side of the road.
- Work expected in the upcoming weeks:
- Continue to identify failed concrete/joint areas, saw cut, remove
and prepare for & place reinforced MS pavement.
- Remove, inspect, rebuild/adjust to grade various manholes, catch
basins and water valve castings.
- Remove and reconstruct existing sidewalk curb ramps to ADA
compliance.
- Place new type-G reflective signage in Sections 1 & 2.
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
May 4, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 2—State Road to Broadview Road
- Work continues on the north side of Snow Road; two-way traffic
will be maintained on the south side of the road.
- Will continue to saw cut, remove and prepare marked pavement areas
for placement of new concrete.
- Remove, inspect and rebuild/adjust to grade various manhole, catch
basin and water valve castings.
- Remove and reconstruct existing sidewalk curb ramps to ADA
compliance.
- Identify and mark areas designated for partial asphalt depth
repairs.
- Backfill/landscape areas along the back of new curbs.
WEEKLY PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
April 3, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
September 2009
PROJECT AMOUNT
$3,505,486.11
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 2—State Road to Broadview Road
- On Friday, March 27, 2009, a work zone was established to resume
the work of repairing and resurfacing Snow Road from approximately
800’ west of State Road to Broadview Road intersection. At this time,
work will occur on the north side of the road while two-way traffic
(one lane in each direction) will be maintained on the south side.
Delays can be expected.
Work expected in the upcoming weeks:
- Removal of existing asphalt surface wearing course.
- Concrete pavement in need of full depth or partial depth repairs
will be identified and marked for removal and replacement.
- Begin to saw cut, remove and prepare marked pavement areas for
placement of new concrete.
- Remove and inspect existing roadway castings, rebuild and adjust
to grade various manholes, catch basins and water valve castings. New
iron casting will be used in areas as designated.
WEEKLY PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
Wednesday, March 25, 2009
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
November 28, 2009
PROJECT AMOUNT
$2,887,359.00
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
- Phase II of the project, from Broadview Road to State Road, will
begin on Friday, March 27, 2009, after the morning rush hour. Two-way
traffic will be maintained at all times on the south side of the
roadway. Construction will occur on the north side of the roadway.
WEEKLY PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
Friday, August 1, 2008
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
November 28, 2008
PROJECT AMOUNT
$2,887,359.00
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 1—State Road to Ridge Road
Phase A—North Side of Snow
- The asphalt intermediate course has been placed and the
castings have been adjusted to grade.
Phase B—South Side of Snow
- The existing asphalt material has been removed from the
surfaces of pavement along Snow Road and the intersections of W.
54th St., W. 60th St. and W. 67th
St.
- Partial/full depth repairs to the existing concrete base are
being identified for removal and replacement
- Catch basins are being adjusted to grade.
WEEKLY PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
Tuesday, August 26, 2008
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
November 28, 2008
PROJECT AMOUNT
$2,887,359.00
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 1—State Road to Ridge Road
Phase A—North Side of Snow
- This section of work has been completed pending the final
paving of surface course scheduled for later this year. Currently,
two-way traffic is being maintained on this section of roadway.
Phase B—South Side of Snow
- The contractor continues to saw, cut and remove partial and
full depth sections of existing pavement that were previously
identified as deteriorated.
- All catch basins, manholes and water valves are being adjusted
or reconstructed to grade. This includes the placement of new
metal castings.
WEEKLY PROJECT UPDATE
SNOW ROAD REPAIR & RESURFACING
RIDGE ROAD TO BROADVIEW ROAD
PARMA
DATE
Friday, October 3, 2008
NOTICE TO PROCEED
June 2, 2008
START DATE
June 2, 2008
COMPLETION DATE
November 28, 2008
PROJECT AMOUNT
$2,887,359.00
CONTRACTOR
Blaze Construction, Inc.
FUNDING
Federal Highway Administration through NOACA, Cuyahoga County and the
City of Parma
PROGRESS
Section 1—State Road to Ridge Road
Phase A—North Side of Snow
- All pavement repairs, casting adjustments, curb ramp
reconstruction and asphalt resurfacing have been completed. On
September 24, all barrels and signs were removed and Snow Road was
opened to full width traffic, curb to curb.
- In the upcoming weeks, punch list items will be completed,
along with the installation of pavement markings to include new
stop lines, cross walk lines and school zone markings.
This page has been accessed times
since February 26, 2004
and was last updated on
Wednesday, September 09, 2009.
© 1999-2008 Cuyahoga County Engineer's Office |