CONSTRUCTION PROJECT UPDATE
OLD ROYALTON BRIDGE #107
REPLACEMENT
CITY OF BRECKSVILLE
DATE
August 19, 2010
NOTICE TO PROCEED
July 6, 2010
START DATE
July 6, 2010
COMPLETION DATE
July 2011
PROJECT AMOUNT
$1,427,294.86
PROGRESS
Project has encountered some utility delays.
- The Perk Company, Inc. has performed the bridge closure and has
placed the detour in effect.
- Demolition work has begun including removal of the bridge deck,
center pier and forward abutment wall.
- Work continues and the closure and detour is expected to continue
until July 2011.
CONSTRUCTION PROJECT UPDATE
OLD ROYALTON BRIDGE #107
REPLACEMENT
CITY OF BRECKSVILLE
DATE
July 16, 2010
NOTICE TO PROCEED
July 6, 2010
START DATE
July 6, 2010
COMPLETION DATE
July 2011
PROJECT AMOUNT
$1,427,294.86
PROGRESS
Bridge was closed on July 15th and will remain closed
until July 2011
- Demolition of the bridge is underway, this project is a complete
demolition and rebuild project.
- Maintenance of traffic signing is in place.
This page has been accessed times
since February 26, 2004
and was last updated on
Thursday, August 19, 2010.