DATE:
September 1, 2010
NOTICE TO PROCEED
May 10, 2010
START DATE
May 17, 2010
COMPLETION DATE
August 2011
PROJECT AMOUNT
$3,221,336.40
PROGRESS
- SECTION 1: Broadview Road to Seven Hills/Independence Corporation
Line
- Repair work has now been completed on the north and south sides of
the roadway.
- Vandra Brothers Construction, Inc. is expecting to take delivery of
pavement fabric material for the final phase of construction can be
completed in September.
- Delays should be expected during the asphalt paving operations
and throughout the morning and evening rush hours. Work expected in
the upcoming weeks:
- Installation of reinforced pavement fabric and asphalt concrete
surface course along the entire pavement width of roadway.
- Placement of top soil and seeding for final landscaping of tree
lawns.
- Install final pavement striping and restore traffic to full width
pavement.
- Removal of construction barrels, maintenance of traffic signage and
reprogram traffic signals back to pre-construction phases.
- Restore regular mail services to the north and south side of
Pleasant Valley Road.
- Punch list items.
SECTION 2: Seven Hills/Independence Corporation Line to Brecksville
Road
Section 2 construction is slated for Spring 2011
ADDITIONAL INFORMATION:
Field Office Phone: 216-901-0155 Email:
pvroad@att.net
Field Office Fax: 216-901-0152 Twitter:
www.twitter.com/pvroad
CONSTRUCTION PROJECT UPDATE
PLEASANT VALLEY ROAD IMPROVEMENT
BROADVIEW RD. TO BRECKSVILLE RD.
CITIES OF INDEPENDENCE & SEVEN HILLS
DATE:
July 30, 2010
NOTICE TO PROCEED
May 10, 2010
START DATE
May 17, 2010
COMPLETION DATE
August 2011
PROJECT AMOUNT
$3,221,336.40
PROGRESS
- SECTION 1: Broadview Road to Seven Hills/Independence Corporation
Line
- Repair work has now been completed on the north side of roadway;
work has now been shifted to the south side of roadway.
- Vandra Brothers Construction, Inc. continues working along the south
side of Pleasant Valley Road; two-way traffic is now maintained on the
intermediate asphalt base pavement in the eastbound lanes (north side of
Pleasant Valley Road) Delays are to be expected during the asphalt
paving operations and throughout the morning and evening rush hours.
Work expected in the upcoming weeks:
- Partial depth removal of existing pavement in areas exhibiting
surface deterioration, application of tack coat and placement of
compacted asphalt concrete.
- Inspect, clean and hot tar sealing of pavement/repair joints and
existing cracks.
- Inspect existing roadway castings: rebuild and adjust to grade
various manhole, catch basin and water valve castings. New iron casting
will be used in areas as designated.
- Roadway clean up and placement of intermediate base course asphalt.
- Installation of reinforced pavement fabric and asphalt concrete
surface course along the entire pavement width of roadway.
- Installation of 6’x30" traffic signal detector loops.
SECTION 2: Seven Hills/Independence Corporation Line to Brecksville
Road
Section 2 construction is slated of Spring 2011
ADDITIONAL INFORMATION:
Field Office Phone: 216-901-0155 Email:
pvroad@att.net
Field Office Fax: 216-901-0152 Twitter:
www.twitter.com/pvroad
CONSTRUCTION PROJECT UPDATE
PLEASANT VALLEY ROAD IMPROVEMENT
BROADVIEW RD. TO BRECKSVILLE RD.
CITIES OF INDEPENDENCE & SEVEN HILLS
DATE:
July 9, 2010
NOTICE TO PROCEED
May 10, 2010
START DATE
May 17, 2010
COMPLETION DATE
August 2011
PROJECT AMOUNT
$3,221,336.40
PROGRESS
- SECTION 1: Broadview Road to Seven Hills/Independence Corporation
Line
- Repair work has now been completed on the north side of the road;
work has now Been shifted to the south side.
- Vandra Brothers Construction, Inc. is now working along the south
side of Pleasant Valley Road; two-way traffic is now maintained on the
intermediate asphalt base pavement in the eastbound lanes (north side of
Pleasant Valley Road).
- Delays are to be expected especially at morning and evening rush
hours.
- Work expected in the upcoming weeks:
- Concrete pavement in need of full depth or partial depth repairs
will be identified and marked for removal and replacement.
- Inspect existing roadway castings; rebuild and adjust to grade
various manhole, catch basin and water valve castings.
- New iron casting will be used in areas as designated.
- Begin removal of existing sidewalk/curb ramps and begin layout and
construction of new ADA compliant ones.
- Inspect existing pressure relief joints for repair/replacement.
- SECTION 2: Seven Hills/Independence Corporation Line to Brecksville
Road
- Section 2 construction is slated for Spring 2010
ADDITIONAL INFORMATION:
Field Office Phone: 216-901-0155 Email:
pvroad@att.net
Field Office Fax: 216-901-0152 Twitter:
www.twitter.com/pvroad
CONSTRUCTION PROJECT UPDATE
PLEASANT VALLEY ROAD IMPROVEMENT
BROADVIEW RD. TO BRECKSVILLE RD.
CITIES OF INDEPENDENCE & SEVEN HILLS
DATE:
May 24, 2010
NOTICE TO PROCEED
May 10, 2010
START DATE
May 17, 2010
COMPLETION DATE
August 2011
PROJECT AMOUNT
$3,221,336.40
PROGRESS
Work continues along the north side of Pleasant Valley Road.
Two-way traffic maintained on the existing pavement in the
eastbound lanes (south side of Pleasant Valley Road.)
- Delays are to be expected especially during morning and evening rush
hours.
Work expected in the upcoming weeks:
Concrete pavement in need of full depth or partial depth repairs
will be identified
and marked for removal and replacement.
- Inspect existing roadway castings; rebuild and adjust to grade
various manhole,
catch basin and water valve castings. New iron casting will be used
in areas as
designated.
- Begin removal of existing sidewalk/curb ramps and begin layout and
construction
of new ADA compliant ones.
- Inspect existing pressure relief joints for repair/replacement.
SECTION 2: Seven Hills/Independence Corporation Line to
Brecksville Road.
Construction is slated for Spring 2011.
ADDITIONAL INFORMATION:
Field Office Phone: 216-901-0155 Email:
pvroad@att.net
Field Office Fax: 216-901-0152 Twitter:
www.twitter.com/pvroad
This page has been accessed times
since February 26, 2004
and was last updated on
Wednesday, September 01, 2010.
© 1999-2010 Cuyahoga County Engineer's Office |