CONSTRUCTION PROJECT UPDATE

PLEASANT VALLEY ROAD IMPROVEMENT

BROADVIEW RD. TO BRECKSVILLE RD.

CITIES OF INDEPENDENCE & SEVEN HILLS

DATE:

September 1, 2010

NOTICE TO PROCEED

May 10, 2010

START DATE

May 17, 2010

COMPLETION DATE

August 2011

PROJECT AMOUNT

$3,221,336.40

PROGRESS

  • SECTION 1: Broadview Road to Seven Hills/Independence Corporation Line
  • Repair work has now been completed on the north and south sides of the roadway.
  • Vandra Brothers Construction, Inc. is expecting to take delivery of pavement fabric material for the final phase of construction can be completed in September.
  • Delays should be expected during the asphalt paving operations and throughout the morning and evening rush hours. Work expected in the upcoming weeks:
  • Installation of reinforced pavement fabric and asphalt concrete surface course along the entire pavement width of roadway.
  • Placement of top soil and seeding for final landscaping of tree lawns.
  • Install final pavement striping and restore traffic to full width pavement.
  • Removal of construction barrels, maintenance of traffic signage and reprogram traffic signals back to pre-construction phases.
  • Restore regular mail services to the north and south side of Pleasant Valley Road.
  • Punch list items.

SECTION 2: Seven Hills/Independence Corporation Line to Brecksville Road

Section 2 construction is slated for Spring 2011

 

ADDITIONAL INFORMATION:

Field Office Phone: 216-901-0155 Email: pvroad@att.net

Field Office Fax: 216-901-0152 Twitter: www.twitter.com/pvroad

 

 

 

 

CONSTRUCTION PROJECT UPDATE

PLEASANT VALLEY ROAD IMPROVEMENT

BROADVIEW RD. TO BRECKSVILLE RD.

CITIES OF INDEPENDENCE & SEVEN HILLS

DATE:

July 30, 2010

NOTICE TO PROCEED

May 10, 2010

START DATE

May 17, 2010

COMPLETION DATE

August 2011

PROJECT AMOUNT

$3,221,336.40

PROGRESS

  • SECTION 1: Broadview Road to Seven Hills/Independence Corporation Line
  • Repair work has now been completed on the north side of roadway; work has now been shifted to the south side of roadway.
  • Vandra Brothers Construction, Inc. continues working along the south side of Pleasant Valley Road; two-way traffic is now maintained on the intermediate asphalt base pavement in the eastbound lanes (north side of Pleasant Valley Road) Delays are to be expected during the asphalt paving operations and throughout the morning and evening rush hours.

Work expected in the upcoming weeks:

  • Partial depth removal of existing pavement in areas exhibiting surface deterioration, application of tack coat and placement of compacted asphalt concrete.
  • Inspect, clean and hot tar sealing of pavement/repair joints and existing cracks.
  • Inspect existing roadway castings: rebuild and adjust to grade various manhole, catch basin and water valve castings. New iron casting will be used in areas as designated.
  • Roadway clean up and placement of intermediate base course asphalt.
  • Installation of reinforced pavement fabric and asphalt concrete surface course along the entire pavement width of roadway.
  • Installation of 6’x30" traffic signal detector loops.

 

 

SECTION 2: Seven Hills/Independence Corporation Line to Brecksville Road

Section 2 construction is slated of Spring 2011

 

 

ADDITIONAL INFORMATION:

Field Office Phone: 216-901-0155 Email: pvroad@att.net

Field Office Fax: 216-901-0152 Twitter: www.twitter.com/pvroad

 

 

 

CONSTRUCTION PROJECT UPDATE

PLEASANT VALLEY ROAD IMPROVEMENT

BROADVIEW RD. TO BRECKSVILLE RD.

CITIES OF INDEPENDENCE & SEVEN HILLS

DATE:

July 9, 2010

NOTICE TO PROCEED

May 10, 2010

START DATE

May 17, 2010

COMPLETION DATE

August 2011

PROJECT AMOUNT

$3,221,336.40

PROGRESS

  • SECTION 1: Broadview Road to Seven Hills/Independence Corporation Line
  • Repair work has now been completed on the north side of the road; work has now Been shifted to the south side.
  • Vandra Brothers Construction, Inc. is now working along the south side of Pleasant Valley Road; two-way traffic is now maintained on the intermediate asphalt base pavement in the eastbound lanes (north side of Pleasant Valley Road).
  • Delays are to be expected especially at morning and evening rush hours.
  • Work expected in the upcoming weeks:
  • Concrete pavement in need of full depth or partial depth repairs will be identified and marked for removal and replacement.
  • Inspect existing roadway castings; rebuild and adjust to grade various manhole, catch basin and water valve castings.
  • New iron casting will be used in areas as designated.
  • Begin removal of existing sidewalk/curb ramps and begin layout and construction of new ADA compliant ones.
  • Inspect existing pressure relief joints for repair/replacement.
  • SECTION 2: Seven Hills/Independence Corporation Line to Brecksville Road
  • Section 2 construction is slated for Spring 2010

 

 

ADDITIONAL INFORMATION:

Field Office Phone: 216-901-0155 Email: pvroad@att.net

                           Field Office Fax: 216-901-0152 Twitter: www.twitter.com/pvroad

 

 

CONSTRUCTION PROJECT UPDATE

PLEASANT VALLEY ROAD IMPROVEMENT

BROADVIEW RD. TO BRECKSVILLE RD.

CITIES OF INDEPENDENCE & SEVEN HILLS

DATE:

May 24, 2010

NOTICE TO PROCEED

May 10, 2010

START DATE

May 17, 2010

COMPLETION DATE

August 2011

PROJECT AMOUNT

$3,221,336.40

PROGRESS

  • Work continues along the north side of Pleasant Valley Road.
  • Two-way traffic maintained on the existing pavement in the

eastbound lanes (south side of Pleasant Valley Road.)

  • Delays are to be expected especially during morning and evening rush hours.

Work expected in the upcoming weeks:

  • Concrete pavement in need of full depth or partial depth repairs will be identified

and marked for removal and replacement.

  • Inspect existing roadway castings; rebuild and adjust to grade various manhole,

catch basin and water valve castings. New iron casting will be used in areas as

designated.

  • Begin removal of existing sidewalk/curb ramps and begin layout and construction

of new ADA compliant ones.

  • Inspect existing pressure relief joints for repair/replacement.

SECTION 2: Seven Hills/Independence Corporation Line to Brecksville Road.

Construction is slated for Spring 2011.

ADDITIONAL INFORMATION:

Field Office Phone: 216-901-0155 Email: pvroad@att.net

Field Office Fax: 216-901-0152 Twitter: www.twitter.com/pvroad

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Wednesday, September 01, 2010.

© 1999-2010 Cuyahoga County Engineer's Office