CONSTRUCTION PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

October 27, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

October 30, 2009 (Revised)

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section One (Richmond Road to Lander Road):
    • All repairs and final surface course asphalt paving in this section of the roadway has been completed.
    • Two-way traffic has been restored.
    • Work expected in the upcoming weeks includes:
    • Gutter and longitudinal joint sealing.
    • Placement of concrete ADA curb ramps and walk on the north side of Lander/Ridgebury.
    • Permanent short line in-laid striping: crosswalk lines, stop lines & arrows.
    • Landscaping restoration and clean-up.
    • Punch list items
    • Section Two (from Lander Road to S.O.M. Center Road):
    • Work continues along the north side of Ridgebury Blvd.
    • Local one-way traffic (eastbound only) maintained on the newly placed surface course of asphalt.
    • A detour route has been established for westbound motorists: SOM Center Road (north) to Wilson Mills Road (west) to Lander Road (south).
    • PLEASE NOTE (WEATHER PERMITTING) TWO-WAY TRAFFIC WILL BE RESTORED ON WEDNESDAY, OCTOBER 28th.
    • Work expected in the upcoming weeks includes:
    • Backfilling/landscaping behind curb repair areas.
    • Permanent short line in-laid striping: crosswalk lines, stop lines & arrows.
    • Punch list item

Additional Information

Field Office Phone: 440-460-4630 Email: ridgeburyproject@att.net

Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd

 

 

CONSTRUCTION PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

September 9, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

October 30, 2009 (Revised)

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section One (Richmond Road to Lander Road):
    • All repairs to this section have been completed.
    • Two-way traffic is being maintained on the newly placed intermediate asphalt course.
    • Roadway castings are raised 1.5" (ramped) in preparation of future placement of surface course.
  • Section Two (from Lander Road to S.O.M. Center Road):
    • Work continues along the south side of Ridgebury Blvd.
    • Local one-way traffic eastbound is being maintained n the newly placed intermediate asphalt on the north side of the road.
    • A detour route has been established for westbound motorists: SOM Center Road (north) to Wilson Mills Road 9west) to Lander Road (south).
  • Work expected in the upcoming weeks includes:
    • Concrete curb repairs
    • Placement of intermediate asphalt to repaired concrete base.
    • Installation of traffic loop detectors.
    • Inspect existing roadway castings and rebuild and adjust to grade various manhole, catch basin and water valve castings. New iron casting will be used in areas as designated.

Additional Information:

Field Office Phone: 440-460-4630 Email: ridgeburyproject@att.net

Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd

 

 

CONSTRUCTION PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

August 10, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

October 30, 2009 (Revised)

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section One (Richmond Road to Lander Road): All repairs to this section of roadway have been completed. Two-way traffic is being maintained on the newly placed intermediate asphalt course. Roadway castings are raised 1.5" in preparation of future placement of surface course.
  • Section Two (from Lander Road to S.O.M. Center Road): Work continues along the north side of Ridgebury Boulevard. Local one-way eastbound traffic will be maintained on the existing surfaces on the south side of the road. Westbound motorists will be detoured north on S.O.M. Center Road, west on Wilson Mills Road and south on Lander Road.
  • Work expected in the upcoming weeks includes:
    • The identification of concrete pavement in need of full-depth or partial-depth repairs. They will then be marked for removal and replaced.
    • The placement of intermediate asphalt to repaired concrete base.
    • The inspection of existing roadway castings. The rebuilding and adjusting to grade various manhole, catch basins and water valve castings. New iron castings will be used in areas as designated.

Additional Information:

Field Office Phone: 440-460-4630 Email: ridgeburyproject@att.net

Field Office Fax: 216-274-9321 Twitter

 

 

CONSTRUCTION PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

July 6, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

November 2009

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section One, from Richmond Road to Lander Road, is scheduled to be completed by July 31, 2009.
  • Section Two, from Lander Road to S.O.M. Center Road, is scheduled to begin the week of July 13, 2009.
  • Local traffic is maintained one-way eastbound throughout the course of construction. Westbound motorists will be detoured to Wilson Mills Road. Weather permitting, two-way traffic will be restored in Section One at the end of July 2009.

Additional Information:

Field Office Phone: 440-460-4630 Email: ridgeburyproject@att.net

Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd

 

 

 

CONSTRUCTION PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

June 30, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

August 20, 2010

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section 1—Richmond Road to Lander Road
      • Work continues along the north side of Ridgebury Blvd. with local one-way traffic (Eastbound only) maintained on the newly intermediate asphalt surfaces on the south side of the roadway. A detour route has been established for Westbound motorists: Lander Road (North) to Wilson Mill Road (West) to Richmond Road (South).

Work expected in the upcoming weeks will include:

  • Concrete pavement in need of full-depth or partial-depth repairs will be identified and marked for removal and replacement.
  • Placement of intermediate asphalt to repaired concrete base.
  • Begin construction of new ADA curb ramps.
  • Inspect existing roadway castings.
  • Rebuild and adjust to grade various manhole, catch basin and water valve castings. New iron casting will be used in areas as designated.

Sometime during the week of July 13, 2009, work will begin on the north side of Ridgebury Section 2 (Lander Road to S.O.M. Center Road). This work will include:

  • Removal of existing asphalt surface wearing course.
  • Concrete pavement in need of full-depth or partial-depth repairs will be identified and marked for removal and replacement.

Additional Information:

Field Office Phone: 440-460-4630 Email: ridgeburyproject@att.net

Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd

 

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

DATE

June 3, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

August 20, 2010

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Section 1—Richmond Road to Lander Road
    • Work continues along the south side of Ridgebury Blvd. Local one-way traffic (eastbound only) will be maintained on the existing surfaces of the north side of the road. A detour route has been established for westbound motorists: Lander Road (north) to Wilson Mills Road (west) to Richmond Road (south).
    • Work to be expected in the upcoming weeks:
      • Begin construction of new ADA curb ramps.
      • Continue to inspect existing roadway castings, rebuild and adjust to grade various manhole, catch basin and water valve castings. New iron casting will be used in areas as designated.
      • Sometime mid-June, one-way traffic will be shifted to the south side of the road so reconstruction work can take place along the north side. This work will include the removal of existing asphalt surface wearing course, identifying full depth or partial depth repairs of concrete pavement and marking these for removal and replacement.

 

WEEKLY PROJECT UPDATE

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

 

DATE

May 4, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

August 20, 2010

PROJECT AMOUNT

$2,345,000

PROGRESS

Section I—Richmond Road to Lander Road

  • Work continues along the south side of Ridgebury Boulevard.
  • Local one-way traffic eastbound is being maintained on the north side of the road. A detour route has been established for westbound motorists: Lander Road to Wilson Mills Road to Richmond Road.
  • Will complete the removal of existing asphalt surface wearing course.
  • Will identify concrete pavement in need of full depth or partial depth repairs. Then will mark them for removal and replacement.
  • Begin to saw cut, remove and prepare marked pavement areas for placement of new concrete.
  • Remove and inspect existing roadway castings, rebuild and adjust to grade various manhole, catch basin and water valve castings.

ADDITIONAL INFORMATION

Field Office Phone: 440-460-4630

Field Office Fax: 216-274-9321

Email: ridgeburyproject@att.net

Twitter: www.twitter.com/Ridgebury Blvd

 

 

RIDGEBURY BOULEVARD REPAIR & RESURFACING

RICHMOND ROAD TO S.O.M. CENTER ROAD

HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND MAYFIELD VILLAGE

 

DATE

April 15, 2009

NOTICE TO PROCEED

April 13, 2009

START DATE

April 20, 2009

COMPLETION DATE

August 20, 2010

PROJECT AMOUNT

$2,345,000

PROGRESS

  • Local traffic will be maintained one-way eastbound throughout the course of construction. The following is the detour for westbound motorists: Richmond Road to Wilson Mills Road to Lander Road to Ridgebury Boulevard.
  • Traffic pattern will be set up on Friday, April 17, 2009.

 

 

 

 