The Cuyahoga County Engineer's Office
Construction Projects Update
CONSTRUCTION PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
October 27, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
October 30, 2009 (Revised)
PROJECT AMOUNT
$2,345,000
PROGRESS
- Section One (Richmond Road to Lander Road):
- All repairs and final surface course asphalt paving in this
section of the roadway has been completed.
- Two-way traffic has been restored.
- Work expected in the upcoming weeks includes:
- Gutter and longitudinal joint sealing.
- Placement of concrete ADA curb ramps and walk on the north side of
Lander/Ridgebury.
- Permanent short line in-laid striping: crosswalk lines, stop lines
& arrows.
- Landscaping restoration and clean-up.
- Punch list items
- Section Two (from Lander Road to S.O.M. Center Road):
- Work continues along the north side of Ridgebury Blvd.
- Local one-way traffic (eastbound only) maintained on the newly
placed surface course of asphalt.
- A detour route has been established for westbound motorists: SOM
Center Road (north) to Wilson Mills Road (west) to Lander Road
(south).
- PLEASE NOTE (WEATHER PERMITTING) TWO-WAY TRAFFIC WILL BE RESTORED
ON WEDNESDAY, OCTOBER 28th.
- Work expected in the upcoming weeks includes:
- Backfilling/landscaping behind curb repair areas.
- Permanent short line in-laid striping: crosswalk lines, stop lines
& arrows.
- Punch list item
Additional Information
Field Office Phone: 440-460-4630 Email:
ridgeburyproject@att.net
Field Office Fax: 216-274-9321 Twitter:
www.twitter.com/RidgeburyBlvd
CONSTRUCTION PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
September 9, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
October 30, 2009 (Revised)
PROJECT AMOUNT
$2,345,000
PROGRESS
Section One (Richmond Road to Lander Road):
- All repairs to this section have been completed.
- Two-way traffic is being maintained on the newly placed
intermediate asphalt course.
- Roadway castings are raised 1.5" (ramped) in preparation of future
placement of surface course.
Section Two (from Lander Road to S.O.M. Center Road):
- Work continues along the south side of Ridgebury Blvd.
- Local one-way traffic eastbound is being maintained n the newly
placed intermediate asphalt on the north side of the road.
- A detour route has been established for westbound motorists: SOM
Center Road (north) to Wilson Mills Road 9west) to Lander Road
(south).
Work expected in the upcoming weeks includes:
- Concrete curb repairs
- Placement of intermediate asphalt to repaired concrete base.
- Installation of traffic loop detectors.
- Inspect existing roadway castings and rebuild and adjust to grade
various manhole, catch basin and water valve castings. New iron
casting will be used in areas as designated.
Additional Information:
Field Office Phone: 440-460-4630 Email:
ridgeburyproject@att.net
Field Office Fax: 216-274-9321 Twitter:
www.twitter.com/RidgeburyBlvd
CONSTRUCTION PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
August 10, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
October 30, 2009 (Revised)
PROJECT AMOUNT
$2,345,000
PROGRESS
Section One (Richmond Road to Lander Road): All repairs to this
section of roadway have been completed. Two-way traffic is being
maintained on the newly placed intermediate asphalt course. Roadway
castings are raised 1.5" in preparation of future placement of surface
course.
Section Two (from Lander Road to S.O.M. Center Road): Work continues
along the north side of Ridgebury Boulevard. Local one-way eastbound
traffic will be maintained on the existing surfaces on the south side of
the road. Westbound motorists will be detoured north on S.O.M. Center
Road, west on Wilson Mills Road and south on Lander Road.
Work expected in the upcoming weeks includes:
- The identification of concrete pavement in need of full-depth or
partial-depth repairs. They will then be marked for removal and
replaced.
- The placement of intermediate asphalt to repaired concrete base.
- The inspection of existing roadway castings. The rebuilding and
adjusting to grade various manhole, catch basins and water valve
castings. New iron castings will be used in areas as designated.
Additional Information:
Field Office Phone: 440-460-4630 Email:
ridgeburyproject@att.net
Field Office Fax: 216-274-9321 Twitter
CONSTRUCTION PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
July 6, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
November 2009
PROJECT AMOUNT
$2,345,000
PROGRESS
- Section One, from Richmond Road to Lander Road, is scheduled to be
completed by July 31, 2009.
- Section Two, from Lander Road to S.O.M. Center Road, is scheduled to
begin the week of July 13, 2009.
- Local traffic is maintained one-way eastbound throughout the course
of construction. Westbound motorists will be detoured to Wilson Mills
Road. Weather permitting, two-way traffic will be restored in Section
One at the end of July 2009.
Additional Information:
Field Office Phone: 440-460-4630 Email:
ridgeburyproject@att.net
Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd
CONSTRUCTION PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
June 30, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
August 20, 2010
PROJECT AMOUNT
$2,345,000
PROGRESS
- Section 1—Richmond Road to Lander Road
- Work continues along the north side of Ridgebury Blvd. with
local one-way traffic (Eastbound only) maintained on the newly
intermediate asphalt surfaces on the south side of the roadway. A
detour route has been established for Westbound motorists: Lander
Road (North) to Wilson Mill Road (West) to Richmond Road (South).
Work expected in the upcoming weeks will include:
- Concrete pavement in need of full-depth or partial-depth repairs
will be identified and marked for removal and replacement.
- Placement of intermediate asphalt to repaired concrete base.
- Begin construction of new ADA curb ramps.
- Inspect existing roadway castings.
- Rebuild and adjust to grade various manhole, catch basin and water
valve castings. New iron casting will be used in areas as designated.
Sometime during the week of July 13, 2009, work will begin on the north
side of Ridgebury Section 2 (Lander Road to S.O.M. Center Road). This work
will include:
Removal of existing asphalt surface wearing course.
Concrete pavement in need of full-depth or partial-depth repairs
will be identified and marked for removal and replacement.
Additional Information:
Field Office Phone: 440-460-4630 Email:
ridgeburyproject@att.net
Field Office Fax: 216-274-9321 Twitter: www.twitter.com/RidgeburyBlvd
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
June 3, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
August 20, 2010
PROJECT AMOUNT
$2,345,000
PROGRESS
Section 1—Richmond Road to Lander Road
- Work continues along the south side of Ridgebury Blvd. Local
one-way traffic (eastbound only) will be maintained on the existing
surfaces of the north side of the road. A detour route has been
established for westbound motorists: Lander Road (north) to Wilson
Mills Road (west) to Richmond Road (south).
- Work to be expected in the upcoming weeks:
- Begin construction of new ADA curb ramps.
- Continue to inspect existing roadway castings, rebuild and
adjust to grade various manhole, catch basin and water valve
castings. New iron casting will be used in areas as designated.
- Sometime mid-June, one-way traffic will be shifted to the south
side of the road so reconstruction work can take place along the
north side. This work will include the removal of existing asphalt
surface wearing course, identifying full depth or partial depth
repairs of concrete pavement and marking these for removal and
replacement.
WEEKLY PROJECT UPDATE
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
May 4, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
August 20, 2010
PROJECT AMOUNT
$2,345,000
PROGRESS
Section I—Richmond Road to Lander Road
- Work continues along the south side of Ridgebury Boulevard.
- Local one-way traffic eastbound is being maintained on the north
side of the road. A detour route has been established for westbound
motorists: Lander Road to Wilson Mills Road to Richmond Road.
- Will complete the removal of existing asphalt surface wearing
course.
- Will identify concrete pavement in need of full depth or partial
depth repairs. Then will mark them for removal and replacement.
- Begin to saw cut, remove and prepare marked pavement areas for
placement of new concrete.
- Remove and inspect existing roadway castings, rebuild and adjust to
grade various manhole, catch basin and water valve castings.
ADDITIONAL INFORMATION
Field Office Phone: 440-460-4630
Field Office Fax: 216-274-9321
Email:
ridgeburyproject@att.net
Twitter: www.twitter.com/Ridgebury Blvd
RIDGEBURY BOULEVARD REPAIR & RESURFACING
RICHMOND ROAD TO S.O.M. CENTER ROAD
HIGHLAND HEIGHTS, LYNDHURST, MAYFIELD HEIGHTS AND
MAYFIELD VILLAGE
DATE
April 15, 2009
NOTICE TO PROCEED
April 13, 2009
START DATE
April 20, 2009
COMPLETION DATE
August 20, 2010
PROJECT AMOUNT
$2,345,000
PROGRESS
Local traffic will be maintained one-way eastbound throughout the
course of construction. The following is the detour for westbound
motorists: Richmond Road to Wilson Mills Road to Lander Road to
Ridgebury Boulevard.
Traffic pattern will be set up on Friday, April 17, 2009.