The Cuyahoga County Engineer's Office

Construction Projects Update

 


WEEKLY PROJECT UPDATE

W. 130TH STREET BRIDGE REHABILITATION

BROOKPARK & PARMA

 

WEEK

  • August 17, 2010

NOTICE TO PROCEED

  • May 10, 2010

COMPLETION DATE

  • October 22, 2010

PROGRESS

 

  • Section 2, Phase A (small section of W. 130th Street near Brookpark Road) is near completion.
  • Next week it is anticipated to switch to the projects last phase (Section 2, Phase B outside traffic lanes in the above section).
  • Two-way traffic will be maintained.

 

 

 

WEEKLY PROJECT UPDATE

W. 130TH STREET BRIDGE REHABILITATION

BROOKPARK & PARMA

 

WEEK

  • August 2 , 2010

NOTICE TO PROCEED

  • May 10, 2010

COMPLETION DATE

  • October 22, 2010

PROGRESS

 

  • Phase 1 will be completed on August 2, 2010 (from Snow Road to 500’ south of Brookpark Road).

 

  • The traffic zone for Phase 2 will be in place by end of business day on August 2nd.

 

  • Phase 2 involves the repairing and resurfacing of West 130th Street 500’ south of Brookpark Road.
  • Lane closures will be posted, two-way traffic will be maintained.

 

 

 

WEEKLY PROJECT UPDATE

W. 130TH STREET BRIDGE REHABILITATION

BROOKPARK & PARMA

 

WEEK

  • July 15, 2010

NOTICE TO PROCEED

  • May 10, 2010

COMPLETION DATE

  • October 22, 2010

PROJECT AMOUNT

  • $1.641,141.72

PROGRESS

 

  • Phase 1 (from Snow Road to 400’ south of Brookpark Road) is 90% complete.
  • All asphalt work to be completed in Phase 1 by Monday, July 20th.
  • Project will be completed with the exception of Phase 2 which is the work on the south side of the West 130th Street/Brookpark Road Intersection.
  • Phase 1 will be completely open to through traffic.
  • Phase 2 will have limited amount of traffic lanes, but two-way traffic will be maintained at all times.
  • Project will be completed when Phase 2 is finished.
  • Completion date is scheduled for late August, early September.

 

 

 

 

 

 

WEEKLY PROJECT UPDATE

W. 130TH STREET BRIDGE REHABILITATION

BROOKPARK & PARMA

 

WEEK

  • May 13, 2010

NOTICE TO PROCEED

  • May 10, 2010

COMPLETION DATE

  • October 22, 2010

PROGRESS

  • Two-way traffic is being maintained on the westside of W. 130th Street

while work progresses on the east half of W. 130th Street.

 

 

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Wednesday, August 18, 2010.