WEEKLY PROJECT UPDATE
WILSON MILLS ROAD RESURFACING
APPROXIMATELY 500’ WEST OF RICHMOND ROAD TO LANDER ROAD
HIGHLAND HEIGHTS & RICHMOND HEIGHTS
DATE
Thursday, May 10, 2007
NOTICE TO PROCEED
May 14, 2007
START DATE
May 14, 2007
COMPLETION DATE
October 18, 2007
PROJECT AMOUNT
$2,004,633.10
PROGRESS
Contractor will move on site on Monday, May 14, 2007.
Traffic will be maintained at all times, but delays are to be expected
WEEKLY PROJECT UPDATE
WILSON MILLS ROAD RESURFACING
APPROXIMATELY 500’ WEST OF RICHMOND ROAD TO LANDER ROAD
HIGHLAND HEIGHTS & RICHMOND HEIGHTS
DATE
Monday, July 23, 2007
NOTICE TO PROCEED
May 14, 2007
START DATE
May 14, 2007
COMPLETION DATE
October 18, 2007
PROJECT AMOUNT
$2,004,633.10
PROGRESS
SECTION 1-Richmond Road to Ford Road
- The intermediate course is completed full width.
- Work is continuing on the north side. This includes adjusting catch
basins, manholes and water valves. Barrels are being used to limit the
roadway to one way in work zone.
- The installation of ADA ramps and sidewalks continues.
- Full depth repairs are occurring in various locations
SECTION 2-Ford Road to Lander Road
- The intermediate course if completed and the roadway is open to full
traffic width.
- All castings are adjusted to grade, and ADA ramps, sidewalks and
reconstructed curbs are completed.
WEEKLY PROJECT UPDATE
WILSON MILLS ROAD RESURFACING
APPROXIMATELY 500’ WEST OF RICHMOND ROAD TO LANDER ROAD
HIGHLAND HEIGHTS & RICHMOND HEIGHTS
DATE
Tuesday, September 4, 2007
NOTICE TO PROCEED
May 14, 2007
START DATE
May 14, 2007
COMPLETION DATE
October 18, 2007
PROJECT AMOUNT
$2,004,633.10
PROGRESS
SECTION 1-Richmond Road to Brainard Road
- The intermediate course has been completed full width.
- The adjusting of catch basins, manholes and water valves has been
completed.
- The installation of ADA ramps and sidewalks has been completed.
- Full depth repairs are complete.
- The centerline boxes have been adjusted to grade.
SECTION 2-Brainard Road to Lander Road
- Intermediate course is completed and roadway is open to full width
traffic
- All castings are adjusted to grade and the repairs on ADA ramps,
sidewalks and curb are completed.
- System loop detectors are being installed.
- In section 2, the centerline boxes have been adjusted to grade.
WEEKLY PROJECT UPDATE
WILSON MILLS ROAD RESURFACING
APPROXIMATELY 500’ WEST OF RICHMOND ROAD TO LANDER ROAD
HIGHLAND HEIGHTS & RICHMOND HEIGHTS
DATE
Monday, October 1, 2007
NOTICE TO PROCEED
May 14, 2007
START DATE
May 14, 2007
COMPLETION DATE
October 18, 2007
PROJECT AMOUNT
$2,004,633.10
PROGRESS
SECTION 1-Richmond Road to Ford Road
- Final layer of top course has been placed.
- The loop detectors have been installed.
- MOT permanent striping has been placed.
- Seeding and mulching is in progress
SECTION 2-Ford Road to Lander Road
- The final layer of top course has been placed.
- Loop detectors have been installed.
- MOT permanent striping has been placed.
- Currently installing pedestrian signals
- Seeding and mulching are in progress.
WEEKLY PROJECT UPDATE
WILSON MILLS ROAD RESURFACING
APPROXIMATELY 500’ WEST OF RICHMOND ROAD TO LANDER ROAD
HIGHLAND HEIGHTS & RICHMOND HEIGHTS
DATE
Monday, November 13, 2007
NOTICE TO PROCEED
May 14, 2007
START DATE
May 14, 2007
COMPLETION DATE
October 18, 2007
PROJECT AMOUNT
$2,004,633.10
PROGRESS
Project was completed on October 18, 2007.