CONSTRUCTION PROJECT UPDATE

MAIN STREET BRIDGE NO.36

OVER BALDWIN CREEK

CITIES OF MIDDLEBURG HEIGHTS & STRONGSVILLE

 

DATE:

  • August 2, 2010

NOTICE TO PROCEED

  • June 2, 2010

START DATE

  • June 11, 2010

COMPLETION DATE

  • September 2010

PROJECT AMOUNT

  • $534,267.10

PROGRESS

 

    • This project has experienced a delay of the reconstruction due to the existing location of the City of Cleveland Water Department (CWD) 12" water main along the north side of the bridge.

 

  • The exposed location of the 12’" water main if remained in place would require a re-design and additional piling for the bridge foundation.

 

  • At this time the project is coordinating with the Cleveland Water Department and a relocation of the water main to the north is currently under review by the CWD.

 

  • The re-opening of the bridge may be delayed from the scheduled date of August 23rd to mid September.

Additional Information:

Darwin Merdes

216-701-1160 Cell

216- 348-4073 Office

 

 

 

 

 

CONSTRUCTION PROJECT UPDATE

MAIN STREET BRIDGE NO.36

OVER BALDWIN CREEK

CITIES OF MIDDLEBURG HEIGHTS & STRONGSVILLE

 

DATE:

  • July 15, 2010

NOTICE TO PROCEED

  • June 2, 2010

START DATE

  • June 11, 2010

COMPLETION DATE

  • September 2010

PROJECT AMOUNT

  • $534,267.10

PROGRESS

    • Demolition of the existing bridge is complete.
    • Pilings for new bridge are complete.
    • Footer construction for new abutments will be begin the week of July 19th.

 

 

 

 

 

 

This page has been accessed Hit Counter times since February 26, 2004
and was last updated on Monday, August 02, 2010.

© 1999-2010 Cuyahoga County Engineer's Office