CONSTRUCTION PROJECT UPDATE
MAIN STREET BRIDGE NO.36
OVER BALDWIN CREEK
CITIES OF MIDDLEBURG HEIGHTS & STRONGSVILLE
DATE:
NOTICE TO PROCEED
START DATE
COMPLETION DATE
PROJECT AMOUNT
$534,267.10
PROGRESS
-
The exposed location of the 12’" water main if
remained in place would require a re-design and additional piling for
the bridge foundation.
-
At this time the project is coordinating with the
Cleveland Water Department and a relocation of the water main to the
north is currently under review by the CWD.
-
The re-opening of the bridge may be delayed from the
scheduled date of August 23rd to mid September.
Additional Information:
Darwin Merdes
216-701-1160 Cell
216- 348-4073 Office
CONSTRUCTION PROJECT UPDATE
MAIN STREET BRIDGE NO.36
OVER BALDWIN CREEK
CITIES OF MIDDLEBURG HEIGHTS & STRONGSVILLE
DATE:
NOTICE TO PROCEED
June 2, 2010
START DATE
June 11, 2010
COMPLETION DATE
September 2010
PROJECT AMOUNT
$534,267.10
PROGRESS
Demolition of the existing bridge is complete.
Pilings for new bridge are complete.
Footer construction for new abutments will be begin the week of
July 19th.